Canada Lithium Project Update

TSX: CLQ; U.S. OTC: CLQMF

TORONTO, June 20, 2013 /CNW Telbec/ - Canada Lithium Corp. ("Canada Lithium" or the "Company") (TSX: CLQ) (U.S. OTC: CLQMF) announced today that the first lithium carbonate samples have been produced from its mine and processing plant near Val d'Or, Québec. The kiln, recently granted operational approval by the Canadian Standards Association (CSA), is functioning at design temperatures, and commissioning of downstream components of the hydrometallurgical plant is ongoing.

Production Schedules and Global Lithium Markets

Due to previously announced delays to the commissioning of the kiln, initial carbonate shipments to Tewoo Group in China have been re-scheduled to July, and ramp-up to annual design capacity of 20,000 tonnes of lithium carbonate is now re-scheduled to be completed in Q1, 2014 (rather than late in Q4 of this year), which may impact the Company's working capital levels. The global market for lithium carbonate, meanwhile, is firm. Strong demand continues for consumer electronics devices, such as laptops, iPads and cellphones powered by lithium-ion batteries. In the electric vehicle/hybrid sector, recent press releases by a major hybrid carmaker indicating a sixfold increase in lithium battery production for its hybrid range of vehicles and Tesla's indications that it could potentially double production of its Model S electric vehicle continue to support lithium carbonate demand.

Tailings Management Facility

Under the supervision of geotechnical consultant, Golder Associates, repairs to the Tailings Management Facility (TMF) have been completed and operations approval has been received from the Ministère du Développement durable, de l'Environnement de la Faune et des Parcs (MDDEFP).

About Canada Lithium Corp.

The Company holds a 100% interest in the Québec Lithium Project near Val d'Or, the geographical heart of the Québec mining industry. It has completed construction and is in the commissioning phase of an open-pit mine and on-site processing plant with estimated capacity to produce approximately 20,000 tonnes of battery-grade lithium carbonate annually. Metallurgical tests have produced battery-grade lithium carbonate samples. A five-year off-take agreement for a minimum of 12,000 tonnes per year was recently signed with Tewoo-ERDC, one of China's largest commodities traders. A second off-take for up to 5,000 tonnes per year was recently signed with Marubeni Corp., a major Japanese commodities trading company. Lithium carbonate is used in lithium-ion batteries that power consumer electronics (laptops, tablets, etc.), power-grid storage facilities and electric and hybrid vehicles. For more information regarding the Company, please refer to the Company's public filings available at www.sedar.com and www.canadalithium.com including, in particular, the Company's Management Discussion and Analysis for the year ended December 31, 2012 and its Annual Information Form for the year ended December 31, 2012 and the Financials and MD&A for the three-month period ended March 31, 2013. The Company trades under the symbol CLQ on the TSX and on the U.S. OTCQX under the symbol CLQMF.

Cautionary Statement Regarding Forward-Looking Information

This press release contains "forward-looking information" within the meaning of Canadian securities legislation. Forward-looking information is based upon the Company's beliefs, estimates and opinions as at the date of this press release, which the Company believes are reasonable, but no assurance can be given that these will prove to be correct. Furthermore, the Company undertakes no obligation to update or revise forward-looking information contained herein if these beliefs, estimates and opinions or other circumstances should change, except as otherwise required by applicable law.

Forward-looking information relates to future events or to future conditions, performance or results of operations and reflects current expectations or beliefs regarding such matters including, but not limited to, information or statements with respect to: (i) the amount of mineral resources; (ii) exploration, development and production activities, including information regarding the potential mineralization and resources; (iii) the amount of future output over any period; (iv) net present value and internal rates of return of the mining operation; (v) assumptions relating to capital costs, operating costs and other cost metrics; (vi) assumptions relating to gross revenues, operating cash flow and other revenue metrics; (vii) assumptions relating to future price and demand for lithium and other macroeconomic metrics; (viii) exploration and development plans, including anticipated costs and timing thereof, time frames for completion, and anticipated time to production; (ix) mine potential and expected mine life; and * sources of and anticipated financing requirements.

All information other than matters of historical fact may be forward-looking information. In some cases, forward-looking information can be identified by the use of words such as "seek", "expect", "anticipate", "budget", "plan", "project", "estimate", "assume", "continue", "forecast", "intend", "believe", "predict", "potential", "target", "strategy", "goal", "may", "could", "would", "might", or "will" and similar words or phrases (including negative variations) suggesting future outcomes or statements regarding an outlook.

Forward-looking information is based upon certain assumptions by the Company or its consultants and other important factors that, if untrue, could cause the actual results, performances or achievements of the Company to be materially different from future results, performances or achievements expressed or implied by such information. Such information is based on numerous assumptions regarding present and future business strategies and the environment in which the Company will operate in the future, including the price of lithium, anticipated costs and ability to achieve goals. Certain important factors that could cause actual results, performances or achievements to differ materially from those in the forward-looking information include, but are not limited to: (i) required capital investment and estimated workforce requirements; (ii) estimates of net present value and internal rates of return; (iii) future demand and market prices for lithium; (iv) receipt of regulatory approvals on acceptable terms within commonly experienced time frames; (v) anticipated timelines for the commencement of production; (vi) anticipated timelines for community consultations and the impact of those consultations on the regulatory approval process; and (vii) future exploration plans and objectives.

By its nature, forward-looking information involves known and unknown risks, uncertainties and other factors which may cause actual results, performance or achievements, or industry results, to differ materially from those expressed or implied by such forward-looking information. Some of the risks and other factors that could cause actual results to differ materially from those expressed in the forward-looking information contained in this press release include, but are not limited to, risks and uncertainties relating to: (i) the interpretation of drill results, the geology, grade and continuity of mineral deposits and conclusions of economic evaluations; (ii) results of feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations, (iii) the outcome of litigation in which the Company is or may in the future become involved; (iv) risks relating to possible variations in reserves, grade, planned mining dilution and ore loss, or recovery rates and changes in project parameters as plans continue to be refined; (v) mining and development risks, including risks related to accidents, equipment breakdowns, labor disputes (including work stoppages and strikes) or other unanticipated difficulties with or interruptions in exploration and development; (vi) risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; (vii) risks related to future commodity demand and price and foreign exchange rate fluctuations; (viii) the uncertainty of profitability based upon the cyclical nature of the industry in which the Company operates; (ix) risks related to failure to obtain adequate financing on a timely basis and on acceptable terms or delays in obtaining governmental approvals or in the completion of development or construction activities; * risks related to environmental regulation and liability; (xi) political and regulatory risks associated with mining and exploration; (xii) risks related to the uncertain global economic environment; and (xiii) other risks and uncertainties related to the Company's prospects, properties and business strategy. Although the Company has attempted to identify important factors that could cause actual results or events to differ materially from those described in the forward-looking information, investors and others are cautioned that this list is not exhaustive and there may be other factors that the Company has not identified. Readers are cautioned not to place undue reliance on forward-looking information contained in this press release. All forward-looking information contained in this press release or incorporated by reference herein is expressly qualified by this cautionary note. For more information on the risks, uncertainties and assumptions that could cause the Company's actual results to differ from current expectations, please refer to the Company's public filings available at www.sedar.com and www.canadalithium.com including, in particular, the "Risks and Uncertainties" section of the Company's Management Discussion and Analysis and the "Risk Factors" section of the Company's Annual Information Form for the year ended December 31, 2012.

SOURCE Canada Lithium Corp.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

DXWorldEXPO Digital Transformation Stories
Data center, on-premise, public-cloud, private-cloud, multi-cloud, hybrid-cloud, IoT, AI, edge, SaaS, PaaS... it's an availability, security, performance and integration nightmare even for the best of the best IT experts. Organizations realize the tremendous benefits of everything the digital transformation has to offer. Cloud adoption rates are increasing significantly, and IT budgets are morphing to follow suit. But distributing applications and infrastructure around increases risk, introdu...
Over the course of two days, in addition to insightful conversations and presentations delving into the industry's current pressing challenges, there was considerable buzz about digital transformation and how it is enabling global enterprises to accelerate business growth. Blockchain has been a term that people hear but don't quite understand. The most common myths about blockchain include the assumption that it is private, or that there is only one blockchain, and the idea that blockchain is...
Atmosera delivers modern cloud services that maximize the advantages of cloud-based infrastructures. Offering private, hybrid, and public cloud solutions, Atmosera works closely with customers to engineer, deploy, and operate cloud architectures with advanced services that deliver strategic business outcomes. Atmosera's expertise simplifies the process of cloud transformation and our 20+ years of experience managing complex IT environments provides our customers with the confidence and trust tha...
Where many organizations get into trouble, however, is that they try to have a broad and deep knowledge in each of these areas. This is a huge blow to an organization's productivity. By automating or outsourcing some of these pieces, such as databases, infrastructure, and networks, your team can instead focus on development, testing, and deployment. Further, organizations that focus their attention on these areas can eventually move to a test-driven development structure that condenses several l...
The term "digital transformation" (DX) is being used by everyone for just about any company initiative that involves technology, the web, ecommerce, software, or even customer experience. While the term has certainly turned into a buzzword with a lot of hype, the transition to a more connected, digital world is real and comes with real challenges. In his opening keynote, Four Essentials To Become DX Hero Status Now, Jonathan Hoppe, Co-Founder and CTO of Total Uptime Technologies, shared that ...
At CloudEXPO Silicon Valley, June 24-26, 2019, Digital Transformation (DX) is a major focus with expanded DevOpsSUMMIT and FinTechEXPO programs within the DXWorldEXPO agenda. Successful transformation requires a laser focus on being data-driven and on using all the tools available that enable transformation if they plan to survive over the long term. A total of 88% of Fortune 500 companies from a generation ago are now out of business. Only 12% still survive. Similar percentages are found throug...
Never mind that we might not know what the future holds for cryptocurrencies and how much values will fluctuate or even how the process of mining a coin could cost as much as the value of the coin itself - cryptocurrency mining is a hot industry and shows no signs of slowing down. However, energy consumption to mine cryptocurrency is one of the biggest issues facing this industry. Burning huge amounts of electricity isn't incidental to cryptocurrency, it's basically embedded in the core of "mini...
Cloud-Native thinking and Serverless Computing are now the norm in financial services, manufacturing, telco, healthcare, transportation, energy, media, entertainment, retail and other consumer industries, as well as the public sector. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that pro...
Every organization is facing their own Digital Transformation as they attempt to stay ahead of the competition, or worse, just keep up. Each new opportunity, whether embracing machine learning, IoT, or a cloud migration, seems to bring new development, deployment, and management models. The results are more diverse and federated computing models than any time in our history.
Dion Hinchcliffe is an internationally recognized digital expert, bestselling book author, frequent keynote speaker, analyst, futurist, and transformation expert based in Washington, DC. He is currently Chief Strategy Officer at the industry-leading digital strategy and online community solutions firm, 7Summits.