Allana Potash Announces Positive Feasibility Study at Its Danakhil Potash Project

Investor Conference Call planned for February 4th, 2013 at 3:00 p.m. EST

TORONTO, ONTARIO -- (Marketwire) -- 02/04/13 -- Allana Potash Corp. (TSX:AAA) (OTCQX:ALLRF)

--  After-tax Net Present Value of US $1.32 billion, based on lower price
    expectations in current potash markets 
--  After-tax Internal Rate of Return of 33% 
--  Production capital expenditures including mining and processing
    facilities ("Production CAPEX") of US$579 million 
--  Port and logistics infrastructure ("Infrastructure CAPEX") of US $63
--  Total CAPEX Contingencies of US$64 million included in the Production
    and Infrastructure CAPEX estimates 
--  Total production operating expenditures ("Production OPEX") of
--  Total transportation expenditures ("Transportation OPEX") (including
    transportation/handling, port, loading costs) FOB on Vessel of
--  Based on Annual Production of one million tonnes of MOP per year using
    solution mining from Proven and Probable Sylvinite Mineral Reserves only
--  Significant Carnallitite or Kainitite resources not included in the
    production plans in this Feasibility Study 

Allana Potash Corp. ("Allana" or the "Company") announces the results of a positive independent Feasibility Study ("FS") prepared by Ercosplan Ingenieurgesellschaft Geotechnik und Bergbau ("ERCOSPLAN") on its Danakhil Potash Project in Ethiopia (the "Project"). Allana's Board of Directors is pleased to congratulate the people and government of the Federal Democratic Republic of Ethiopia on the receipt by Allana of the first NI 43-101-compliant feasibility study on a potash resource in Ethiopia's Danakhil potash basin that defines one of the few economically viable greenfield potash projects in the world.

The FS is based on commercial operations that produce one million tonnes per year ("MTPY") of a standard grade Muriate of Potash ("MOP") product over an initial estimated operating life of approximately 25 years from Sylvinite Reserves at Allana's Danakhil Project in Ethiopia. The FS yielded, on an unlevered basis, an after-tax Internal Rate of Return ("IRR") of 33 % and an after-tax Net Present Value ("NPV") of US$ 1.32 billion based on a 10% discount rate.

Farhad Abasov, President and CEO of Allana commented: "Allana is extremely pleased with the very positive Feasibility Study of its Danakhil Potash Project, as prepared by ERCOSPLAN. Even with current potash market realities driving the lower potash price forecast of USD $430/tonne used in the FS, the favourable total production CAPEX of about US$579 million and port and transport CAPEX of US$63 million, make this project one of the lowest cost and potentially highest return greenfield potash projects worldwide. Similarly, the very competitive production OPEX at US$69.25/tonne, within a total, loaded-on-ship, OPEX of US$98.75/tonne FOB, is one of the lowest among greenfield potash projects currently under development."

Mr. Abasov added, "ERCOSPLAN modeled the production of one million tonnes of MOP from just the Sylvinite Zone on the project, excluding future potential production from the extensive Carnallite and sulphate-based Kainite resources. The FS's extremely positive results give Allana great confidence in advancing its project to development and securing project finance and offtake."

The key economic highlights of the FS are outlined in the table below (all dollar amounts are stated in US$):

After-tax [email protected]%                                               $1.32billion
After-tax IRR (based on 35% income tax rate)                             33%
Estimated Total Capital Expenditures (including                             
 production, port and logistics and contingency)                $642 million
Estimated Total Operating Expenditures (Production,                         
 transportation, port, FOB on vessel)                       $98.75/tonne MOP
Payback period                                                     3.1 years
Total MOP product from Proven and Probable Sylvinite                        
 Reserves,                                               23.7 million tonnes

For the purpose of the FS, capital expenditures (CAPEX) were estimated for three main categories: Production using solution mining, solar evaporation and flotation (Production); Transportation and handling of product between the production site and the port (Transportation/Handling); and Port facilities in Djibouti (Port).

The Production CAPEX includes costs associated with cavern development, the solar evaporation ponds, brine processing, and infrastructure including power. Solar evaporation of the saturated brine solution is possible at the Danakhil Project due to the year-round hot temperatures averaging 34 degrees C daylong with very little rainfall. Salts harvested from the ponds will be processed by standard flotation to create an MOP product of a standard grade sufficient for direct application as fertilizer or as feedstock for processed or blended fertilizers.

Transportation CAPEX costs are based on a company owned fleet of trucks and all support, such as maintenance. Port CAPEX costs are based on Allana constructing its own storage facility and conveyor system at the new port of Tadjourah in Djibouti. The main portion of the port, primarily the quay, ship loader and associated infrastructure, is commencing construction and will be completed by the Djibouti Port Authority. The table below outlines the estimated capital expenditures in US$ (2013$) for all categories, including indirects and allocated contingencies.

Total Estimated CAPEX                         $642 million
  Estimated Production CAPEX                  $579 million
  Estimated Transportation/Handling CAPEX      $29 million
  Estimated Port CAPEX                         $34 million

Estimated operating expenditures (OPEX) were also calculated for Production, Transportation/Handling, and Port. The OPEX costs in US$ per tonne (2013$), including G&A and contingencies, are outlined in the table below:

Total Estimated OPEX                           $98.75/tonne
  Estimated Production OPEX                    $69.25/tonne
  Estimated Transportation/Handling/Port OPEX  $29.50/tonne

Estimated sustaining capital during operations is estimated at US$ 24.3 million (2013$) per year once operations reach steady state full production at 1 MTPY.

The economic analysis performed in the FS was based on the following assumptions:

Production:      One million tonnes MOP per year from Sylvinite, with first 
                 product in 2015, and bulk shipments ramping up from 2016 to
                 full 1 MTPY production rate by the end of 2017             
Mine life:       25 years, based on currently defined reserves of Sylvinite 
Mining method:   Solution mining                                            
Processing:      Solar evaporation and flotation                            
Transport:       Trucking to Djibouti                                       
Power:           Power generation with fuel oil shipped to site             
Potash Price:    US$430 per tonne (2013$)                                   
Underlying NSR:  1.5% (after partial buyout of royalty)                     

The economic analysis also included government tax and levies based on current Ethiopian published legislation and regulation, assuming:

Government Royalties:              4% on revenue
Government free carried interest:             5%
Corporate taxes:                             35%

The FS estimates include all infrastructure required to operate a potash solution mine and to bring the product to market including cavern and wellfield installation, three stage processing plant, product storage facilities, load out, trucking fleet and port storage facilities with all necessary infrastructure.

Summary of Mineral Reserve and Resource Estimates Update

The Company also announces that as a result of the proposed mine plan and favourable economic results developed in the FS, portions of the previously reported measured and indicated sylvinite mineral resource estimates have been upgraded to proven and probable sylvinite mineral reserves. Estimates of the updated mineral reserves and mineral resources were completed by ERCOSPLAN based on a Radius of Influence (ROI) as per industry standards. The following Tables outline the current estimated sylvinite mineral resources and proven and probable sylvinite mineral reserves. All Measured and Indicated Sylvinite Resources were converted to Reserves.

Summary of Mineral Resource Estimates effective as of February 2, 2013

Measured         115.31        27.8        32.0
Indicated        212.11        28.6        60.7
Inferred          90.76        27.8        25.2

(i)ROI for measured, indicated and inferred Sylvinite mineral resource estimates are 350 metres, 750 metres and 1500 metres respectively. Cut-off grade is 15% KCl, minimum width is 1.5 metres, density average 2.15

Mineral resources which are not mineral reserves do not have demonstrated economic viability. The estimates of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

The quantity and grade of reported inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource and it is uncertain if further exploration will result in upgrading them to an indicated or measured mineral resource category

Summary of Mineral Reserve Estimates effective as of February 2, 2013.

           MINEABLE TONNES                                
RESERVES          (MT)(ii)         KCL (%)  MOP (M TONNES)
Proven               32.97            28.0             8.2
Probable             60.81            28.8            15.5
TOTAL                                                 23.7

(ii) Accounts for losses in the caverns as well as in pillar material between caverns.

(i)ROI for Proven and Probable Sylvinite Mineral Reserves are 350 metres and 750 respectively. Cut-off grade is 15% KCl, minimum width is 1.5 metres, density average 2.15, potash price of $430/tonne and other key assumptions listed above. The estimates of mineral reserves may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

The Proven and Probable Reserves from Sylvinite zone alone are adequate to support production of 1 million tonnes per year of MOP for approximately 25 years. Pilot testwork continues on site as a second solution mining well is currently leaching the Upper Carnallitite unit to provide data on the production of MOP from a Carnallite-rich brine. The results of this study will be used for potential increase in production tonnage in the future.

The FS, with a cost estimate accuracy of +/- 15%, was completed by ERCOSPLAN, a widely recognized world leader in potash exploration techniques and potash mining and processing. In addition to Allana, ERCOSPLAN's clients include some of the largest potash exploration companies and potash producers in the world. An NI 43-101 technical report with respect to the FS (the "FS Technical Report") and the mineral resource and reserve estimates forming the basis of the FS report will be available under the Company's profile on SEDAR and Allana's website within 45 days of this news release.

The Feasibility Study and the mineral resource and reserve estimates were completed by ERCOSPLAN under the supervision of Dr. Henry Rauche, Ph.D., EurGeol, Managing Director, CEO ERCOSPLAN and Dr. Sebastiaan van der Klauw, Ph.D., EurGeol., Consulting Geologist, ERCOSPLAN who are both independent Qualified Persons for the purposes of National Instrument 43-101. Peter J. MacLean, Ph.D., P. Geo., Allana's Senior VP Exploration, is the Company's designated Qualified Person for the purposes of the Feasibility Study and has reviewed and approved the technical information presented in this release.

An Investor conference call and webcast to review the FS results will be held at 3:00 p.m. (EST) today, Monday, February 4, 2013. To participate on the call please dial:

Participant Dial-In Numbers:                  
TOLL-FREE (North America)   1-888-395-3227    
TOLL-FREE INTERNATIONAL     1-719-325-2484    
Replay Dial-In Numbers:                       
TOLL-FREE (North America)   1-877-870-5176    
TOLL-FREE INTERNATIONAL     1-858-384-5517    
Replay Pin Number:          3946278           

(The replay will be available starting at 6:00 p.m. EST today, and archived on www.allanapotash.com for ninety days thereafter).

To view the slide deck during the webcast, please register at:

Webcast Presentation Link:https://viavid.webcasts.com/starthere.jsp?ei=1013058

Please register at least 10 minutes prior to the 3:00 p.m. start. A Q&A session will follow the presentation.

About Allana Potash Corp.

Allana is a publicly traded corporation with a focus on the acquisition and development of potash assets internationally with its major focus on a previously explored potash property in Ethiopia. Allana has secured financial support from two significant strategic investors: IFC, a member of World Bank Group, and Liberty Metals and Mining, a member of Liberty Mutual Group. Allana has measured and indicated Sylvinite resources as at February 2, 2013 of 327.42 million tonnes of 28.31% KCl; and inferred Sylvinite resource of 90.76 million tonnes grading 27.80% KCl, as outlined in this press release. In addition, the Danakhil Projects hosts measured and indicated Kainitite resources of 701.55 million tonnes at 20.26% KCl, inferred Kainitite resource of 373.71 million tonnes of 20.35% KCl; measured and indicated Upper Carnallitite resources of 78.5 million tonnes grading 18.4% KCl, inferred Upper Carnallitite resource of 155.53 million tonnes of 16.95% KCl; measured and indicated Lower Carnallitite resources of 269.10 million tonnes of 10.86% KCl, inferred Lower Carnallitite resource of 130.7 million tonnes grading 11.7% KCl. The foregoing mineral resource estimates with respect to Kainitite and Carnallitite are as at April 27, 2012. For more information with respect to the data verification procedures undertaken and the key assumptions, parameters and risks associated with the foregoing estimates refer to Allana's Technical Report entitled "Updated Resource Report for the Danakhil Potash Deposit, Afar State/Ethiopia" dated June 13, 2012, effective April 30, 2012 filed at www.sedar.com. And the FS Technical Report to be filed on SEDAR within 45 days from the date of this release. Allana has approximately 275.9 million shares outstanding. Allana trades on the Toronto Stock Exchange under the symbol "AAA".

Cautionary Notes

Except for statements of historical fact relating to the Company, certain information contained herein constitutes "forward-looking information" under Canadian securities legislation. Forward-looking information includes, but is not limited to, statements regarding the results of the feasibility study, next steps for the property, progress in development of the property, projected capital and operating expenses, anticipated production schedule, the size and quality of the company's mineral resources and reserves, progress in development of mineral properties, future capital and operating expenses, capital and operating production costs, future potash prices and treatment charges, the financial results of the company the future financial or operating performance of the Company, the prospective mineralization of the properties and planned exploration programs., the issue of permits, future production and sales volumes, capital and production costs, demand and market outlook for potash, planned exploration programs, anticipated production schedule and terms and the availability and likelihood of future acquisitions; government regulation of mining operations; environmental risks; unanticipated reclamation expenses; and title disputes or claims; Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Estimates underlying the results of the feasibility study arise from engineering, geological and costing work of Ercosplan and the Company.

See the FS Technical Report, to be filed within 45 days of this news release, for a description of all relevant estimates, assumptions and parameters. Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking statements or forward-looking information. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements and forward-looking information. The Company does not undertake to update any forward-looking statements or forward-looking information that are incorporated by reference herein, except in accordance with applicable securities laws.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@BigDataExpo Stories
@ThingsExpo has been named the Top 5 Most Influential M2M Brand by Onalytica in the ‘Machine to Machine: Top 100 Influencers and Brands.' Onalytica analyzed the online debate on M2M by looking at over 85,000 tweets to provide the most influential individuals and brands that drive the discussion. According to Onalytica the "analysis showed a very engaged community with a lot of interactive tweets. The M2M discussion seems to be more fragmented and driven by some of the major brands present in the...
DevOps is being widely accepted (if not fully adopted) as essential in enterprise IT. But as Enterprise DevOps gains maturity, expands scope, and increases velocity, the need for data-driven decisions across teams becomes more acute. DevOps teams in any modern business must wrangle the ‘digital exhaust’ from the delivery toolchain, "pervasive" and "cognitive" computing, APIs and services, mobile devices and applications, the Internet of Things, and now even blockchain. In this power panel at @...
SYS-CON Events announced today that Streamlyzer will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Streamlyzer is a powerful analytics for video streaming service that enables video streaming providers to monitor and analyze QoE (Quality-of-Experience) from end-user devices in real time.
You have great SaaS business app ideas. You want to turn your idea quickly into a functional and engaging proof of concept. You need to be able to modify it to meet customers' needs, and you need to deliver a complete and secure SaaS application. How could you achieve all the above and yet avoid unforeseen IT requirements that add unnecessary cost and complexity? You also want your app to be responsive in any device at any time. In his session at 19th Cloud Expo, Mark Allen, General Manager of...
One of biggest questions about Big Data is “How do we harness all that information for business use quickly and effectively?” Geographic Information Systems (GIS) or spatial technology is about more than making maps, but adding critical context and meaning to data of all types, coming from all different channels – even sensors. In his session at @ThingsExpo, William (Bill) Meehan, director of utility solutions for Esri, will take a closer look at the current state of spatial technology and ar...
SYS-CON Events announced today that SoftNet Solutions will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. SoftNet Solutions specializes in Enterprise Solutions for Hadoop and Big Data. It offers customers the most open, robust, and value-conscious portfolio of solutions, services, and tools for the shortest route to success with Big Data. The unique differentiator is the ability to architect and ...
The IoT industry is now at a crossroads, between the fast-paced innovation of technologies and the pending mass adoption by global enterprises. The complexity of combining rapidly evolving technologies and the need to establish practices for market acceleration pose a strong challenge to global enterprises as well as IoT vendors. In his session at @ThingsExpo, Clark Smith, senior product manager for Numerex, will discuss how Numerex, as an experienced, established IoT provider, has embraced a ...
Cloud based infrastructure deployment is becoming more and more appealing to customers, from Fortune 500 companies to SMEs due to its pay-as-you-go model. Enterprise storage vendors are able to reach out to these customers by integrating in cloud based deployments; this needs adaptability and interoperability of the products confirming to cloud standards such as OpenStack, CloudStack, or Azure. As compared to off the shelf commodity storage, enterprise storages by its reliability, high-availabil...
Donna Yasay, President of HomeGrid Forum, today discussed with a panel of technology peers how certification programs are at the forefront of interoperability, and the answer for vendors looking to keep up with today's growing industry for smart home innovation. "To ensure multi-vendor interoperability, accredited industry certification programs should be used for every product to provide credibility and quality assurance for retail and carrier based customers looking to add ever increasing num...
SYS-CON Events announced today that Super Micro Computer, Inc., a global leader in Embedded and IoT solutions, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 7-9, 2017, at the Javits Center in New York City, NY. Supermicro (NASDAQ: SMCI), the leading innovator in high-performance, high-efficiency server technology, is a premier provider of advanced server Building Block Solutions® for Data Center, Cloud Computing, Enterprise IT, Hadoop/Big Data, HPC and ...
In the next forty months – just over three years – businesses will undergo extraordinary changes. The exponential growth of digitization and machine learning will see a step function change in how businesses create value, satisfy customers, and outperform their competition. In the next forty months companies will take the actions that will see them get to the next level of the game called Capitalism. Or they won’t – game over. The winners of today and tomorrow think differently, follow different...
“Media Sponsor” of SYS-CON's 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. CloudBerry Backup is a leading cross-platform cloud backup and disaster recovery solution integrated with major public cloud services, such as Amazon Web Services, Microsoft Azure and Google Cloud Platform.
SYS-CON Events announced today that LeaseWeb USA, a cloud Infrastructure-as-a-Service (IaaS) provider, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. LeaseWeb is one of the world's largest hosting brands. The company helps customers define, develop and deploy IT infrastructure tailored to their exact business needs, by combining various kinds cloud solutions.
Successful digital transformation requires new organizational competencies and capabilities. Research tells us that the biggest impediment to successful transformation is human; consequently, the biggest enabler is a properly skilled and empowered workforce. In the digital age, new individual and collective competencies are required. In his session at 19th Cloud Expo, Bob Newhouse, CEO and founder of Agilitiv, will draw together recent research and lessons learned from emerging and established ...
November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Penta Security is a leading vendor for data security solutions, including its encryption solution, D’Amo. By using FPE technology, D’Amo allows for the implementation of encryption technology to sensitive data fields without modification to schema in the database environment. With businesses having their data become increasingly more complicated in their mission-critical applications (such as ERP, CRM, HRM), continued ...
SYS-CON Events announced today that Enzu will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Enzu’s mission is to be the leading provider of enterprise cloud solutions worldwide. Enzu enables online businesses to use its IT infrastructure to their competitive advantage. By offering a suite of proven hosting and management services, Enzu wants companies to focus on the core of their online busine...
Traditional on-premises data centers have long been the domain of modern data platforms like Apache Hadoop, meaning companies who build their business on public cloud were challenged to run Big Data processing and analytics at scale. But recent advancements in Hadoop performance, security, and most importantly cloud-native integrations, are giving organizations the ability to truly gain value from all their data. In his session at 19th Cloud Expo, David Tishgart, Director of Product Marketing ...
SYS-CON Events announced today that Cloudbric, a leading website security provider, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Cloudbric is an elite full service website protection solution specifically designed for IT novices, entrepreneurs, and small and medium businesses. First launched in 2015, Cloudbric is based on the enterprise level Web Application Firewall by Penta Security Sys...
Established in 1998, Calsoft is a leading software product engineering Services Company specializing in Storage, Networking, Virtualization and Cloud business verticals. Calsoft provides End-to-End Product Development, Quality Assurance Sustenance, Solution Engineering and Professional Services expertise to assist customers in achieving their product development and business goals. The company's deep domain knowledge of Storage, Virtualization, Networking and Cloud verticals helps in delivering ...
The best way to leverage your Cloud Expo presence as a sponsor and exhibitor is to plan your news announcements around our events. The press covering Cloud Expo and @ThingsExpo will have access to these releases and will amplify your news announcements. More than two dozen Cloud companies either set deals at our shows or have announced their mergers and acquisitions at Cloud Expo. Product announcements during our show provide your company with the most reach through our targeted audiences.