Click here to close now.

Welcome!

Big Data Journal Authors: Liz McMillan, Pat Romanski, Elizabeth White, William Schmarzo, Dana Gardner

News Feed Item

Stornoway Reports Optimized Renard Mine Design and Cost Estimates

Initial Capital Cost Reduced; High Operating Margin Maintained

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 01/28/13 -- Stornoway Diamond Corporation (TSX:SWY) is pleased to report the completion of a mine design and cost optimization exercise (the "Optimization Study") for the Renard Diamond Project, Stornoway's 100% owned mining development project located in north-central Quebec. The Optimization Study incorporates certain design refinements undertaken since the release of the project's Feasibility Study in November 2011 (the "Feasibility Study"), including the deferral of shaft access for the underground mine and a modified underground mining sequence and draw point design. As a result of these design changes, project operating and capital cost estimates have been restated, and a revised production schedule established. The Optimization Study also contains an updated project development schedule and financial model incorporating, amongst other things, the terms of the March 2012 Mecheshoo Agreement with the Cree Nation of Mistissini, the Grand Council of the Crees (Eeyou Istchee), and the Cree Regional Authority, and the November 2012 Renard Mine Road financing agreement with the Government of Quebec. Highlights of the Optimization Study are as follows:


--  A revised initial capital cost of C$752 million, including
    contingencies, in October 2012 terms, a reduction of C$50 million from
    the previous estimate which was expressed in June 2011 terms. 
--  A revised operating cost averaging C$57.63/tonne (C$76.63/carat) life of
    mine in October 2012 terms, an increase of C$2.92/tonne from the
    previous estimate. 
--  Base case estimates of Net Present Value ("NPV") of C$683 million at a
    7% discount rate and Internal Rate of Return ("IRR") of 20.3% before
    taxes and mining duties, and C$391 million and 16.3% after taxes and
    mining duties, all improvements from the previous estimates. 
--  11 years reserve-based mine life with diamond production averaging 1.6
    million carats/annum life of mine, real terms net revenue of C$4,046
    million, and a cash operating margin of C$2,693 million (67% compared to
    68% in the previous estimate).

Matt Manson, President and CEO, commented: "The Optimization Study reported today confirms a robust project with strong cash flows. Since the release of the project's Feasibility Study, we have been able to bring down our initial capital cost estimate with only a modest impact on the project's operating costs. We are particularly pleased that the project has so successfully absorbed the kind of post-feasibility design adjustments and operating agreements that can negatively impact a project's value. The deferral of the shaft has been achieved without compromising the future development of the project's substantial resource upside, and the refinements made to the underground mining sequence provide greater confidence in the operating parameters for this critical part of the overall mine plan. With our Mining Lease and Quebec Certificate of Authorization in hand, and the Renard Mine Road under development, we can now move towards finalizing our project financing arrangements, and initiating project construction in the third quarter of this year."

The Optimization Study restates the project's Probable Mineral Reserves at 17.9 million carats (23.8 Mtonnes at 75 carats per hundred tonnes, or "cpht"), a reduction of 0.1 million carats after allowance for revised mining dilution and ore recovery estimates. The new study does not incorporate any changes to the project's underlying National Instrument ("NI") 43-101 compliant Mineral Resources, and does not include the results of the ongoing bulk sampling program at the Renard 65 kimberlite. Including Renard 65, the project contains 17.5 million carats (31.1 Mtonnes at 56 cpht) of Inferred Mineral Resources, much of which lies within the envelope of the planned mine infrastructure. Since mineral resources that are not mineral reserves do not have demonstrated economic viability, these have not been incorporated into the Optimization Study mine plan, in compliance with Canadian reporting standards. However, the project's design, processed kimberlite storage capacity, permits and Mining Lease contemplates the eventual mining of all NI 43-101 Mineral Resources over an extended mine life. In addition to the Mineral Resources, 23.5 to 48.5 million carats of non-resource exploration upside (55.1 to 75.5 Mtonnes at grades ranging from 23 to 188 cpht) has been estimated to 775 meters depth, below which each kimberlite remains open. Readers are cautioned that the potential quantity and grade of any such exploration target is conceptual in nature, there has been insufficient exploration to define a mineral resource, and it is uncertain if further exploration will result in the target being delineated as a mineral resource (an Optimization Study Support Material presentation is available at http://stornowaydiamonds.com/_resources/feasibility_support_materials_20130128.pdf).

Significant Changes to the November 2011 Feasibility Study

The Feasibility Study included both ramp and shaft access to the Renard underground mine. Shaft sinking will now be deferred until later in the mine life and access to the underground mine will be by way of a ramp only. This will be developed to a depth of 610 meters, sufficient to extract all Mineral Reserves and the Inferred Mineral Resources, and enlarged to accommodate the planned production rate of 6,000 tonnes of ore daily. Ore will be hauled to surface by 60 tonne trucks, with ramp ventilation capacity and surface maintenance facilities expanded to accommodate the increased fleet. Plant capacity remains at 6,000 tonnes per day (2.2 Mtonnes/year) expandable to 7,000 tonnes per day (2.6 Mtonnes/year). Power requirements are expected to total 12.2 MW during operations and be provided by on-site diesel power generation.

Diamond production in Years 1 and 2 remains predominantly derived from the Renard 2/3 open pit. Diamond production from the underground mine will commence during Year 2. As with the Feasibility Study, underground ore will be mined with blast-hole shrinkage on 250 meter, 430 meter and 610 meter development levels, with waste back fill from surface. The Optimization Study contains a refined draw point design and a mining sequence incorporating a panel-retreat method to better assure geomechanical stability and militate against the unexpected onset of natural caving. Numerical analysis of blast fragmentation, and modeling of ore flow during the draw, has been conducted using REBOP(TM) software. This has resulted in a modest increase in the overall estimate for ore dilution and a modest decrease in the estimate for ore recovery.

No changes have been made to assumptions contained within the Feasibility Study for diamond price, exchange rate, or marketing costs. The cost of diesel fuel is based on an assumed oil price of US$95/barrel compared to US$90/barrel previously.

The Optimization Study incorporates the impact of a Framework Agreement between Stornoway and the Quebec Ministere des Transports, the Ministere des Ressources Naturelles, and the Ministere des Finances et de l'Economie ("MFE") for the completion of the Route 167 Extension and the Renard Mine Road, and a revised financing agreement between Stornoway and the MFE (Stornoway press releases dated November 15 and 30, 2012). The Optimization Study assumes a cost to Stornoway of $78 million (after escalation) to complete the road. The MFE loan to Stornoway funding the Renard Mine Road is in two tranches, $77 million at 3.35% and, to the extent required, an additional $7.7 million at 6.3%, both with a term of 15 years, with interest accruing from January 2016 and interest and principal payments beginning in December 2016. As a result of these agreements, the new project development schedule assumes first road access to the project site by the fourth quarter of 2013 rather than July 2013 previously. Plant commissioning is now scheduled to begin in December 2015 with commercial production achieved by June 2016, compared to July 2015 and January 2016 previously.

The Optimization Study also incorporates certain financial terms of the Mecheshoo Agreement, the Impacts and Benefits Agreement between Stornoway, the Cree Nation of Mistissini, the Grand Council of the Crees (Eeyou Istchee) and the Cree Regional Authority (Stornoway press release dated March 27, 2012). The Mecheshoo Agreement includes a mechanism by which the Cree parties will benefit financially from the success of the project on a long term basis, consistent with mining industry best practices for social engagement.

The results of the Optimization Study are outlined in Table 1 below.


Table 1: Results and Key Assumptions         November 2011     January 2013
                                         Feasibility Study     Optimization
---------------------------------------------------------------------------
Mining          Reserve Carats (M)                    18.0             17.9
Parameters                                                                 
                -----------------------------------------------------------
                Tonnes Processed (M)                  23.1             23.8
                -----------------------------------------------------------
                Recovered Grade (cpht)                  78               75
                -----------------------------------------------------------
                Average Ore Recovery (%)             83.5%            82.9%
                -----------------------------------------------------------
                Average Mining Dilution              13.5%            17.9%
                (%)                                                        
                -----------------------------------------------------------
                Dilution Grade (cpht)                    0                0
                -----------------------------------------------------------
                Processing Rate                        2.2              2.2
                (Mtonnes/annum)                                            
                -----------------------------------------------------------
                Mine Life (years)                       11               11
---------------------------------------------------------------------------
Cost Parameters Initial Cap-ex (C$M)(1)               $802             $752
                -----------------------------------------------------------
                LOM Cap-ex (C$M)(3)                   $994           $1,013
                -----------------------------------------------------------
                Oil Price (US$/barrel)(1)              $90              $95
                -----------------------------------------------------------
                LOM Op-ex (C$/tonne)(1)             $54.71           $57.63
                -----------------------------------------------------------
                LOM Op-ex (C$/carat)(1)             $70.27           $76.63
---------------------------------------------------------------------------
Revenue         Gross Revenue (C$M)(1)              $4,112           $4,268
Parameters                                                                 
                -----------------------------------------------------------
                Marketing Costs                       2.7%             2.7%
                -----------------------------------------------------------
                DIAQUEM Royalty                       2.0%             2.0%
                -----------------------------------------------------------
                Cash Operating Margin               $2,677           $2,693
                (C$M)(1)                                                   
                -----------------------------------------------------------
                % Operating Margin                     68%              67%
                -----------------------------------------------------------
                Income Tax, Mining Duties             $571             $625
                and IBA payments (C$M)(1)                                  
                -----------------------------------------------------------
                After Tax Net Cash Flow             $1,151           $1,084
                (C$M)                                                      
---------------------------------------------------------------------------
Diamond Price   Renard 2 and Renard 3                 $182             $182
Parameters(2)   (US$/carat)                                                
                -----------------------------------------------------------
                Renard 4 (US$/carat)                  $164             $164
                -----------------------------------------------------------
                Diamond Price Escalation              2.5%             2.5%
                -----------------------------------------------------------
                Exchange rate                     1C$=1US$         1C$=1US$
---------------------------------------------------------------------------
Schedule        Effective Date for NPV      January 1 2012   January 1 2013
Parameters      Calculation                                                
                -----------------------------------------------------------
                Construction Mobilization      July 1 2013    August 1 2013
                (Early Works)                                              
                -----------------------------------------------------------
                Plant Commissioning            July 1 2015  December 1 2015
                Commences                                                  
                -----------------------------------------------------------
                Commercial Production       January 1 2016      June 1 2016
                Declared                                                   
---------------------------------------------------------------------------
Valuation       Pre-Tax NPV7% (C$M)                   $672             $683
Parameters(4)                                                              
                -----------------------------------------------------------
                Pre-Tax IRR                          18.7%            20.3%
                -----------------------------------------------------------
                After-Tax NPV7% (C$M)                 $376             $391
                -----------------------------------------------------------
                After-Tax IRR                        14.9%            16.3%
---------------------------------------------------------------------------

1.  November 2011 Feasibility Study expressed in June 2011 terms. January
    2013 Optimization expressed in October 2012 terms. 
2.  Prices are expressed in May 2011 terms. 
3.  Expressed in nominal terms. 
4.  De-escalated nominal terms. 

Capital and Operating Costs

Capital and operating costs in the Optimization Study were adjusted on the basis of modified deliverables and material take offs arising from the mine design scope changes. No changes were made to quantity estimates where no design changes had been made. Capital cost is estimated at an accuracy of -11% and +19%. All estimated costs were escalated to October 2012 terms from June 2011 terms previously by applying market inflation indices. Indirect, owners and EPCM costs were re-assessed on the basis of the revised project schedule including early works and infrastructure availability. Contingencies, risk and escalation factors were all re-assessed.

Initial capital costs are now estimated at C$752.1 million, including a contingency of C$64.7 million, expressed in October 2012 terms. Life of Mine capital cost, including escalation commencing in Q4 2012, the Renard Mining Road, sustaining and deferred capital, less credits for pre-production revenue and salvage value, are estimated at C$1,012.9 million.


                                               November 2011               
Table 2: Estimate of Capital Costs(1)            Feasibility   January 2013
                                                       Study   Optimization
---------------------------------------------------------------------------
Site Preparation & General                            $ 22.9         $ 32.7
Mining                                               $ 236.9        $ 151.2
Mineral processing plant                             $ 168.4        $ 175.4
Onsite utilities and infrastructures                 $ 102.4        $ 114.8
Owner's Cost                                          $ 86.2         $ 94.7
Spares, fills, tools                                  $ 10.2          $ 7.1
EPCM services                                         $ 45.0         $ 47.9
Field indirect costs, vendor representatives          $ 22.5         $ 33.9
Construction camp & Catering                          $ 25.0         $ 24.5
Freight and duties                                     $ 8.1          $ 5.5
Contingency                                           $ 74.3         $ 64.7
---------------------------------------------------------------------------
Total Initial Capital                                $ 801.8        $ 752.1
---------------------------------------------------------------------------
Escalation Allowance on Initial Capital               $ 57.3         $ 45.1
Pre-Production Revenue                              $ (24.6)       $ (25.0)
Deferred & Sustaining Capital(2)                     $ 138.8        $ 175.9
Deferred Capital (Route 167 Extension)                $ 44.0          $ 0.0
Renard Mine Road(2)                                    $ 0.0         $ 78.0
Salvage Value(2)                                    $ (22.9)       $ (13.3)
---------------------------------------------------------------------------
Total Life of Mine Capital, After                    $ 994.4      $ 1,012.9
Contingency, Escalation, Deferred and                                      
Sustaining Capital                                                         
---------------------------------------------------------------------------
All figures in C$ million.                                                 
1. Totals may not add due to rounding.                                     
2. After Escalation                                                        

Life of mine operating cost is estimated at C$57.63/tonne (C$76.63 per carat; Table 3). The majority of open pit costs at Renard 2 and 3 occur before June 2016 and are contained within the capital cost estimates.


Table 3: Estimate of Operating Costs(1,2)                                  
                                November 2011            January 2013      
                               Feasibility Study         Optimization      
                           ------------------------------------------------
                                          Unit Cost               Unit Cost
                            C$ millions     $/Tonne C$ millions     $/Tonne
---------------------------------------------------------------------------
Open Pit Mine                       $ 6      $ 0.27        $ 10      $ 0.43
Underground Mine(3)               $ 556     $ 24.45       $ 555     $ 23.64
Processing                        $ 344     $ 15.13       $ 359     $ 15.29
G&A                               $ 338     $ 14.86       $ 429     $ 18.27
---------------------------------------------------------------------------
Total Life of Mine              $ 1,244     $ 54.71     $ 1,352     $ 57.63
Operating Costs                         ($70.27/ct)             ($76.63/ct)
---------------------------------------------------------------------------

1.  Totals may not add due to rounding. November 2011 Feasibility Study
    costs are expressed in Q3 2011 terms. January 2013 Optimization costs
    are expressed in Q3 2012 terms. 
2.  Excludes capitalized preproduction costs. 
3.  Unit cost per processed tonnes. Unit cost per mined tonnes were $26.13
    in the November 2011 Feasibility Study and are $25.53 in the 2013
    Optimization Study.

Qualified Persons

Jean-Francois St-Onge, Eng. of SNC Lavalin Inc. is the independent Qualified Person responsible for infrastructure design, the operating and capital cost estimate, and risk management.

Dr. Lynton Gormely, P.Eng. of AMEC Americas Limited is the independent Qualified Person responsible for process plant design.

Mr. William Bagnell, P.Eng. of AMEC Americas Limited is the independent Qualified Person responsible for underground mine design and mineral reserves.

Mr. Louis-Pierre Gignac, Eng. of G Mining Services Inc. is the independent Qualified Person responsible for open pit design and mineral reserves, and financial analysis.

Mr. Martin Magnan, Eng. of Roche Lte. is the independent Qualified Person responsible for permitting and environmental and social considerations.

Mr. Paul Bedell, P.Eng. of Golder Associates Ltd. is the independent Qualified Person responsible for geotechnical, water management and processed kimberlite containment facility design.

Ms. Valerie Bertrand, Geo. of Golder Associates Ltd. is the independent Qualified Person responsible for geochemical classification.

Dr. Richard Brummer, P.Eng. of Itasca Consulting Canada Inc. is the independent Qualified Person responsible for geomechanical and hydrogeological considerations.

Mr. Charles Gagnon, Eng. of Roscoe Postle Associates Inc. is the independent Qualified Person responsible for underground ventilation design.

Mr. David Farrow, P.Geo. (BC) of GeoStrat Consulting Inc. is the independent Qualified Person responsible for the preparation of the mineral resource estimate for the Renard Diamond Project.

All of these Qualified Persons have reviewed and approved the contents of this press release for which they are responsible.

Stornoway will file a NI 43-101 compliant technical report on the Optimization Study, representing an amended Feasibility Study, within 45 days.

About the Renard Diamond Project

The Renard Diamond Project is located approximately 250 km north of the Cree community of Mistissini and 350 km north of Chibougamau in the James Bay region of north-central Quebec. In November 2011, Stornoway released the Renard results in the November 2011 Feasibility Study followed with the January 2013 Feasibility Study Optimization which highlighted the potential of the project to become a significant producer of high value rough diamonds over a long mine life. NI 43-101 compliant Probable Mineral Reserves stand at 17.9 million carats, with a further 17.5 million carats classified as Inferred Mineral Resources, and 23.5 to 48.5 million carats classified as non-resource exploration upside. All kimberlites remain open at depth. Pre-production capital cost stands at an estimated C$752 million, with a life of mine operating cost of C$57.63/tonne giving a 67% operating margin over an initial 11 year mine life. Readers are referred to the technical report dated December 29, 2011 in respect of the November 2011 Feasibility Study for the Renard Diamond Project for further details and assumptions relating to the project.

About Stornoway Diamond Corporation

Stornoway is a leading Canadian diamond exploration and development company listed on the Toronto Stock Exchange under the symbol SWY and headquartered in Montreal. Our flagship asset is the 100% owned Renard Diamond Project, on track to becoming Quebec's first diamond mine. Stornoway also maintains an active diamond exploration program with both advanced and grassroots programs in the most prospective regions of Canada. Stornoway is a growth oriented company with a world class asset, in one of the world's best mining jurisdictions, in one of the world's great mining businesses.

On behalf of the Board

STORNOWAY DIAMOND CORPORATION

Matt Manson, President and Chief Executive Officer

This press release contains "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995. This information and these statements, referred to herein as "forward-looking statements", are made as of the date of this press release and the Company does not intend, and does not assume any obligation, to update these forward-looking statements, except as required by law.

Forward-looking statements relate to future events or future performance and reflect current expectations or beliefs regarding future events and include, but are not limited to, statements with respect to: (i) the amount of mineral resources and exploration targets; (ii) the amount of future production over any period; (iii) net present value and internal rates of return of the mining operation; (iv) assumptions relating to capital costs, operating costs and other cost metrics set out in the Feasibility Study or the Optimization Study; (v) assumptions relating to gross revenues, operating cash flow and other revenue metrics set out in the Feasibility Study or the Optimization Study; (vi) assumptions relating to recovered grade, average ore recovery and other mining parameters set out in the Feasibility Study or the Optimization Study; (vii) mine expansion potential and expected mine life; (viii) expected time frames for completion of permitting and regulatory approvals and making a production decision; (ix) the expected time frames for delivery of a winter road by the Quebec Ministere des Transports, construction of a mining grade road by Stornoway and completion generally of the Route 167 extension and the financial obligations or costs incurred by Stornoway in connection with such road extension; (x) future exploration plans; (xi) future market prices for rough diamonds; and (xii) sources of and anticipated financing requirements. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "anticipates", "plans", "projects", "estimates", "assumes", "intends", "strategy", "goals", "objectives" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements are made based upon certain assumptions by Stornoway or its consultants and other important factors that, if untrue, could cause the actual results, performances or achievements of Stornoway to be materially different from future results, performances or achievements expressed or implied by such statements. Such statements and information are based on numerous assumptions regarding present and future business strategies and the environment in which Stornoway will operate in the future, including the price of diamonds, anticipated costs and ability to achieve goals. Certain important factors that could cause actual results, performances or achievements to differ materially from those in the forward-looking statements include, but are not limited to: (i) estimated approval date of the Environmental and Social Impact Assessment; (ii) required capital investment and estimated workforce requirements; (iii) estimates of net present value and internal rates of return; (iv) receipt of regulatory approvals on acceptable terms within commonly experienced time frames; (v) the assumption that a production decision will be made, and that decision will be positive; (vi) anticipated timelines for the commencement of mine production; (vii) anticipated timelines related to the delivery of a winter road by the Quebec Ministere des Transports, construction of a mining grade road by Stornoway and completion generally of the Route 167 extension and the impact on the development schedule at Renard; (viii) anticipated timelines for community consultations and the impact of those consultations on the regulatory approval process; (ix) market prices for rough diamonds and the potential impact on the Renard Project's value; and (x) future exploration plans and objectives.

By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. We caution readers not to place undue reliance on these forward-looking statements as a number of important risk factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates, assumptions and intentions expressed in such forward-looking statements. These risk factors may be generally stated as the risk that the assumptions and estimates expressed above do not occur, including the assumption in many forward-looking statements that other forward-looking statements will be correct, but specifically include, without limitation, (i) risks relating to variations in the grade, kimberlite lithologies and country rock content within the material identified as mineral resources from that predicted; (ii) variations in rates of recovery and breakage; (iii) the greater uncertainty of exploration targets; (iv) developments in world diamond markets; (v) slower increases in diamond valuations than assumed; (vi) risks relating to fluctuations in the Canadian dollar and other currencies relative to the US dollar; (vii) increases in the costs of proposed capital and operating expenditures; (viii) increases in financing costs or adverse changes to the terms of available financing if any; (ix) tax rates or royalties being greater than assumed; (x) results of exploration in areas of potential expansion of resources; (xi) changes in development or mining plans due to changes in other factors or exploration results of Stornoway; (xii) changes in project parameters as plans continue to be refined; (xiii) risks relating to receipt of regulatory approvals or the implementation of the existing Impact and Benefits Agreement with aboriginal communities; (xiv) the effects of competition in the markets in which Stornoway operates; (xv) operational and infrastructure risks; (xvi) technical, environmental, permitting and execution risk relating to the construction by Stornoway of a mining grade road forming part of the Route 167 extension, (xvii) weather conditions or other unpredictable events which may impact the construction or planned availability of a winter road by March 2013; and (xviii) the additional risks described in Stornoway's most recently filed Annual Information Form, annual and interim MD&A, and Stornoway's anticipation of and success in managing the foregoing risks. Stornoway cautions that the foregoing list of factors that may affect future results is not exhaustive.

When relying on our forward-looking statements to make decisions with respect to Stornoway, investors and others should carefully consider the foregoing factors and other uncertainties and potential events. Stornoway does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by Stornoway or on our behalf, except as required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@BigDataExpo Stories
As enterprises engage with Big Data technologies to develop applications needed to meet operational demands, new computation fabrics are continually being introduced. To leverage these new innovations, organizations are sacrificing market opportunities to gain expertise in learning new systems. In his session at Big Data Expo, Supreet Oberoi, Vice President of Field Engineering at Concurrent, Inc., discussed how to leverage existing infrastructure and investments and future-proof them against e...
Due of the rise of Hadoop, many enterprises are now deploying their first small clusters of 10 to 20 servers. At this small scale, the complexity of operating the cluster looks and feels like general data center servers. It is not until the clusters scale, as they inevitably do, when the pain caused by the exponential complexity becomes apparent. We've seen this problem occur time and time again. In his session at Big Data Expo, Greg Bruno, Vice President of Engineering and co-founder of StackI...
The true value of the Internet of Things (IoT) lies not just in the data, but through the services that protect the data, perform the analysis and present findings in a usable way. With many IoT elements rooted in traditional IT components, Big Data and IoT isn’t just a play for enterprise. In fact, the IoT presents SMBs with the prospect of launching entirely new activities and exploring innovative areas. CompTIA research identifies several areas where IoT is expected to have the greatest impac...
There is little doubt that Big Data solutions will have an increasing role in the Enterprise IT mainstream over time. 8th International Big Data Expo, co-located with 17th International Cloud Expo - to be held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA - has announced its Call for Papers is open. As advanced data storage, access and analytics technologies aimed at handling high-volume and/or fast moving data all move center stage, aided by the cloud computing bo...
Every day we read jaw-dropping stats on the explosion of data. We allocate significant resources to harness and better understand it. We build businesses around it. But we’ve only just begun. For big payoffs in Big Data, CIOs are turning to cognitive computing. Cognitive computing’s ability to securely extract insights, understand natural language, and get smarter each time it’s used is the next, logical step for Big Data.
The OpenStack cloud operating system includes Trove, a database abstraction layer. Rather than applications connecting directly to a specific type of database, they connect to Trove, which in turn connects to one or more specific databases. One target database is Postgres Plus Cloud Database, which includes its own RESTful API. Trove was originally developed around MySQL, whose interfaces are significantly less complicated than those of the Postgres cloud database. In his session at 16th Cloud...
With major technology companies and startups seriously embracing IoT strategies, now is the perfect time to attend @ThingsExpo in Silicon Valley. Learn what is going on, contribute to the discussions, and ensure that your enterprise is as "IoT-Ready" as it can be! Internet of @ThingsExpo, taking place Nov 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 17th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading in...
SAP is delivering break-through innovation combined with fantastic user experience powered by the market-leading in-memory technology, SAP HANA. In his General Session at 15th Cloud Expo, Thorsten Leiduck, VP ISVs & Digital Commerce, SAP, discussed how SAP and partners provide cloud and hybrid cloud solutions as well as real-time Big Data offerings that help companies of all sizes and industries run better. SAP launched an application challenge to award the most innovative SAP HANA and SAP HANA...
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In his session at Internet of @ThingsExpo, James Kirkland, Chief Ar...
The 17th International Cloud Expo has announced that its Call for Papers is open. 17th International Cloud Expo, to be held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA, brings together Cloud Computing, APM, APIs, Microservices, Security, Big Data, Internet of Things, DevOps and WebRTC to one location. With cloud computing driving a higher percentage of enterprise IT budgets every year, it becomes increasingly important to plant your flag in this fast-expanding bu...
All major researchers estimate there will be tens of billions devices - computers, smartphones, tablets, and sensors - connected to the Internet by 2020. This number will continue to grow at a rapid pace for the next several decades. With major technology companies and startups seriously embracing IoT strategies, now is the perfect time to attend @ThingsExpo, June 9-11, 2015, at the Javits Center in New York City. Learn what is going on, contribute to the discussions, and ensure that your enter...
The security devil is always in the details of the attack: the ones you've endured, the ones you prepare yourself to fend off, and the ones that, you fear, will catch you completely unaware and defenseless. The Internet of Things (IoT) is nothing if not an endless proliferation of details. It's the vision of a world in which continuous Internet connectivity and addressability is embedded into a growing range of human artifacts, into the natural world, and even into our smartphones, appliances, a...
There is no doubt that Big Data is here and getting bigger every day. Building a Big Data infrastructure today is no easy task. There are an enormous number of choices for database engines and technologies. To make things even more challenging, requirements are getting more sophisticated, and the standard paradigm of supporting historical analytics queries is often just one facet of what is needed. As Big Data growth continues, organizations are demanding real-time access to data, allowing immed...
SYS-CON Events announced today that DragonGlass, an enterprise search platform, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. After eleven years of designing and building custom applications, OpenCrowd has launched DragonGlass, a cloud-based platform that enables the development of search-based applications. These are a new breed of applications that utilize a search index as their backbone for data...
SYS-CON Events announced today that EnterpriseDB (EDB), the leading worldwide provider of enterprise-class Postgres products and database compatibility solutions, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. EDB is the largest provider of Postgres software and services that provides enterprise-class performance and scalability and the open source freedom to divert budget from more costly traditiona...
Gartner predicts that the bulk of new IT spending by 2016 will be for cloud platforms and applications and that nearly half of large enterprises will have cloud deployments by the end of 2017. The benefits of the cloud may be clear for applications that can tolerate brief periods of downtime, but for critical applications like SQL Server, Oracle and SAP, companies need a strategy for HA and DR protection. While traditional SAN-based clusters are not possible in these environments, SANless cluste...
Discussions about cloud computing are evolving into discussions about enterprise IT in general. As enterprises increasingly migrate toward their own unique clouds, new issues such as the use of containers and microservices emerge to keep things interesting. In this Power Panel at 16th Cloud Expo, moderated by Conference Chair Roger Strukhoff, panelists will address the state of cloud computing today, and what enterprise IT professionals need to know about how the latest topics and trends affec...
Software Defined Storage provides many benefits for customers including agility, flexibility, faster adoption of new technology and cost effectiveness. However, for IT organizations it can be challenging and complex to build your Enterprise Grade Storage from software. In his session at Cloud Expo, Paul Turner, CMO at Cloudian, looked at the new Original Design Manufacturer (ODM) market and how it is changing the storage world. Now Software Defined Storage companies can build Enterprise grade ...
To manage complex web services with lots of calls to the cloud, many businesses have invested in Application Performance Management (APM) and Network Performance Management (NPM) tools. Together APM and NPM tools are essential aids in improving a business's infrastructure required to support an effective web experience... but they are missing a critical component - Internet visibility. Internet connectivity has always played a role in customer access to web presence, but in the past few years u...
There's Big Data, then there's really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. In her session at Big Data Expo®, Hannah Smalltree, Director at Treasure Data, discussed how IoT, Big D...