Welcome!

Big Data Journal Authors: Pat Romanski, Roger Strukhoff, Michael Bushong, Keith Cawley, Elizabeth White

News Feed Item

Paramount Provides Update on Cavalier Energy Inc.: Probable Reserves Recognized for Hoole Project

CALGARY, ALBERTA -- (Marketwire) -- 01/10/13 -- Paramount Resources Ltd. ("Paramount") (TSX:POU) is pleased to announce that its wholly-owned subsidiary Cavalier Energy Inc. ("Cavalier") has received an updated independent evaluation of the Grand Rapids formation in its 100 percent owned in-situ oil sands leases in the Hoole area of Alberta (the "Hoole Lands").

The evaluation ascribed 93 million barrels of probable reserves with a net present value (discounted at 10 percent) of $379 million to Cavalier's initial 10,000 barrel per day in-situ SAGD oil sands development covering approximately two sections of the Hoole Lands (the "Hoole Project"). Over and above the aforementioned reserves, the evaluation ascribed 719 million barrels of economic contingent resources (best estimate) with a net present value (discounted at 10 percent) of $1.949 billion to the remaining approximate 54 sections of Cavalier's Hoole Lands (the "Remaining Hoole Lands"). "The new estimates further emphasize that the Hoole Lands are a significant asset and the recognition of reserves is an important milestone for Cavalier," stated William Roach, President and Chief Executive Officer of Cavalier.

The updated estimates and reclassification of Hoole Project volumes from economic contingent resources to probable reserves follows Cavalier's November 2012 regulatory applications to the Energy Resources Conservation Board and Alberta Environment and Sustainable Resource Development.

Subject to receipt of regulatory approvals, the Hoole Project schedule currently anticipates first steam in 2015 and the first full year of production in 2016. It is expected that the Hoole Lands could support a project of over 80,000 barrels per day by 2022.

"This is another positive step forward for Paramount and the Cavalier team," said Jim Riddell, President and Chief Operating Officer of Paramount.

Results of the updated evaluation of the Hoole Lands conducted by McDaniel & Associates Consultants Ltd. ("McDaniel"), effective as of December 31, 2012, are summarized below.


Hoole Project - Summary of Bitumen Reserves(1)                    
                                                                  
The evaluation ascribed total proved plus probable plus possible  
 reserves of 104 million barrels to the Hoole Project, implying a 
 recovery factor of approximately 65 percent in relation to the   
 assigned Discovered Exploitable Bitumen In Place(2) of 159       
 million barrels.                                                 
                                                            NPV of
                                                           Future 
                                                               Net
                                                        Revenue(7)
                                                       (discounted
                                           Reserves(6)     at 10%)
------------------------------------------------------------------
                                               (MMBbl)       ($MM)
Total Proved(3)                                      -           -
Probable Undeveloped(4)                             93         379
------------------------------------------------------------------
Total Proved Plus Probable                          93         379
Possible Undeveloped(5)                             11         146
------------------------------------------------------------------
Total Proved + Probable + Possible                 104         525
------------------------------------------------------------------
------------------------------------------------------------------
                                                                            
(1) The estimates of reserves and future net revenue for individual         
    properties may not reflect the same confidence level as estimates of    
    reserves and future net revenue for all properties, due to effects of   
    aggregation.                                                            
(2) Discovered Exploitable Bitumen In Place is the estimated volume of      
    bitumen, as of a given date, which is contained in a subsurface         
    stratigraphic interval of a known accumulation that meets or exceeds    
    certain reservoir characteristics, such as minimum continuous net pay,  
    porosity and mass bitumen content. For the Hoole Project, the presence  
    of these characteristics is considered necessary for the commercial     
    application of known recovery technologies. There is no certainty that  
    it will be commercially viable to produce any portion of the resources  
    from the Hoole Project.                                                 
(3) Proved reserves are those reserves that can be estimated with a high    
    degree of certainty to be recoverable. It is likely that the actual     
    remaining quantities recovered will exceed the estimated proved         
    reserves.                                                               
(4) Probable reserves are those additional reserves that are less certain to
    be recovered than proved reserves. It is equally likely that the actual 
    remaining quantities recovered will be greater or less than the sum of  
    the estimated proved plus probable reserves.                            
(5) Possible reserves are those additional reserves that are less certain to
    be recovered than probable reserves. There is a 10 percent probability  
    that the quantities actually recovered will equal or exceed the sum of  
    proved plus probable plus possible reserves.                            
(6) Working interest volumes, before the deduction of royalties.            
(7) NPV means net present value and represents Cavalier's share of future   
    net revenue, before the deduction of income tax, from reserves in the   
    Grand Rapids formation within the Hoole Project. The calculation        
    considers such items as revenues, royalties, operating costs,           
    abandonment costs and capital expenditures. Royalties have been         
    calculated based on Alberta's Royalty Framework applicable to oil sands 
    projects. The calculation does not consider financing costs and general 
    and administrative costs. NPVs were calculated assuming natural gas is  
    used as a fuel for steam generation. Revenues and expenditures were     
    calculated based on McDaniel's forecast prices and costs as of January  
    1, 2013. The estimated net present values disclosed in this press       
    release do not represent fair market value.                             
                                                                            
Remaining Hoole Lands - Summary of Bitumen Resources                        
                                                                      NPV of
                                                                     Future 
                                                                         Net
                                                        Economic  Revenue(6)
                                                      Contingent (discounted
Classification/Level of Certainty           DEBIP(4)Resources(5)     at 10%)
----------------------------------------------------------------------------
                                             (MMBbl)     (MMBbl)       ($MM)
High Estimate(1)                               1,656         903       2,982
Best Estimate(2)                               1,469         719       1,949
Low Estimate(3)                                1,167         511         946
----------------------------------------------------------------------------
                                                                            
(1) High Estimate is considered to be an optimistic estimate of the quantity
    of resource that will actually be recovered. It is unlikely that the    
    actual remaining quantities of resources recovered will meet or exceed  
    the high estimate. Those resources at the high end for the estimate     
    range have a lower degree of certainty (a 10 percent confidence level)  
    that the actual quantities recovered will equal or exceed the estimate. 
(2) Best Estimate is considered to be the best estimate of the quantity that
    will be actually recovered. It is equally likely that the actual        
    remaining quantities recovered will be greater or less than the best    
    estimate. Those resources that fall within the best estimate have a 50  
    percent confidence level that the actual quantities recovered will equal
    or exceed the estimate.                                                 
(3) Low Estimate is considered to be a conservative estimate of the quantity
    of resources that will actually be recovered. It is likely that the     
    actual remaining quantities recovered will exceed the low estimate.     
    Those resources at the low end of the estimate range have the highest   
    degree of certainty (a 90 percent confidence level) that the actual     
    quantities recovered will equal or exceed the estimate.                 
(4) Discovered Exploitable Bitumen In Place is the estimated volume of      
    bitumen, as of a given date, which is contained in a subsurface         
    stratigraphic interval of a known accumulation that meets or exceeds    
    certain reservoir characteristics, such as minimum continuous net pay,  
    porosity and mass bitumen content. For the Remaining Hoole Lands, the   
    presence of these characteristics is considered necessary for the       
    commercial application of known recovery technologies. There is no      
    certainty that it will be commercially viable to produce any portion of 
    the resources from the Remaining Hoole Lands.                           
(5) Contingent Resources are those quantities of bitumen estimated, as of a 
    given date, to be potentially recoverable from known accumulations using
    established technology or technology under development, but are         
    classified as a resource rather than a reserve due to one or more       
    contingencies, such as the absence of regulatory applications, detailed 
    design estimates or near term development plans. There is no certainty  
    that it will be commercially viable to produce any portion of the       
    contingent resources. For the Remaining Hoole Lands, contingencies which
    must be overcome to enable the reclassification of bitumen contingent   
    resources as reserves include the finalization of plans for the         
    development, submission of a regulatory application and management's    
    intent to proceed evidenced by a development plan with major capital    
    expenditures. Economic Contingent Resources are those contingent        
    resources that are economically recoverable based on specific forecasts 
    of commodity prices and costs (based on McDaniel's forecast prices and  
    costs as of January 1, 2013). Volumes presented are working interest,   
    before the deduction of royalties.                                      
(6) NPV means net present value and represents Cavalier's share of future   
    net revenue, before the deduction of income tax, from the economic      
    contingent resources in the Grand Rapids formation within the Remaining 
    Hoole Lands. The calculation considers such items as revenues,          
    royalties, operating costs, abandonment costs and capital expenditures. 
    Royalties have been calculated based on Alberta's Royalty Framework     
    applicable to oil sands projects. The calculation does not consider     
    financing costs and general and administrative costs. NPVs were         
    calculated assuming natural gas is used as a fuel for steam generation. 
    Revenues and expenditures were calculated based on McDaniel's forecast  
    prices and costs as of January 1, 2013. The estimated net present values
    disclosed in this press release do not represent fair market value.     

The pricing assumptions used in the McDaniel evaluation can be found at www.mcdan.com/pdf/20130101.pdf.

More information pertaining to Cavalier, including its latest corporate presentation, is available at the newly launched Cavalier website at www.cavalierenergy.com and may also be accessed via the Paramount website at www.paramountres.com.

Paramount is a Canadian oil and natural gas exploration, development and production company with operations focused in Western Canada. Paramount's Class A Common Shares are listed on the Toronto Stock Exchange under the symbol "POU".

For further information on the Hoole Project specifically, or Cavalier in general, please go to www.cavalierenergy.com or contact William Roach.

Advisory Regarding Forward-Looking Information:

This news release contains certain forward-looking information under applicable securities legislation. Forward-looking information typically contains statements with words such as "anticipate", "believe", "estimate", "expect", "plan", "intend", "propose", or similar words suggesting future outcomes or an outlook. Forward looking information in this news release includes, but is not limited to: Estimated reserves and resources and the discounted net present value of future net revenues from such reserves and resources (including the forecast prices, costs and the timing of expected production volumes and future development capital) and expected production volumes from the Hoole Lands and the timing thereof.

Such forward looking information is based on a number of assumptions which may prove to be incorrect. The following assumptions have been made, in addition to any other assumptions identified in this document:


--  Future crude oil, bitumen and natural gas prices and general economic
    and business conditions; 
--  The ability to obtain required capital to finance Cavalier's
    exploration, development and operations; 
--  The ability to obtain equipment, services, supplies and personnel in a
    timely manner to carry out its activities; 
--  The ability of Cavalier to successfully market its production; 
--  Estimates of input and labour costs for an oil sands project; 
--  Access to capital markets and other sources of funding; 
--  The ability to secure adequate product processing, transportation and
    storage; 
--  The ability to successfully apply oil sands technology and to capitalize
    on improvements thereto; 
--  The ability to achieve forecast production volumes, steam oil ratios,
    and capital and operating costs consistent with expectations; 
--  The timely receipt of required regulatory approvals and the scope of
    such approvals; 
--  Estimated timelines being met in respect of the development of the Hoole
    Lands; and 
--  Currency exchange and interest rates. 

Although Paramount and Cavalier believe that the expectations reflected in such forward-looking information are reasonable, undue reliance should not be placed on them as neither Paramount nor Cavalier can give any assurance that such expectations will prove to be correct. Forward-looking information is based on current expectations, estimates and projections that involve a number of risks and uncertainties which could cause actual results to differ materially from those anticipated by Paramount and Cavalier and described in the forward-looking information. These risks and uncertainties include, but are not limited to:


--  Fluctuations in crude oil, bitumen and natural gas prices, foreign
    currency exchange rates and interest rates; 
--  The uncertainty of estimates and projections relating to future revenue,
    future production, costs and expenses and the timing thereof; 
--  The ability to secure adequate product processing, transportation and
    storage; 
--  The uncertainty and risks of exploration, development, drilling and the
    geology of bitumen; 
--  Operational risks in exploring for, developing and producing petroleum,
    and the timing thereof; 
--  The ability to obtain equipment, services, supplies and personnel in a
    timely manner; 
--  Potential disruption or unexpected technical difficulties in designing,
    developing and operating facilities; 
--  The uncertainty of reserves and resources estimates; 
--  The ability to obtain financing at an acceptable cost to meet current
    and future obligations including costs of anticipated projects; 
--  Potential lawsuits and regulatory actions; 
--  Changes to the status or interpretation of laws, regulations or
    policies; 
--  Changes in environmental laws including emission reduction obligations; 
--  The receipt, timing and scope of governmental or regulatory approvals; 
--  Changes in general business and economic conditions; 
--  Uncertainty regarding aboriginal land claims and co-existing with local
    populations; 
--  The effects of weather; 
--  The timing and cost of future abandonment and reclamation activities; 
--  Cleanup costs for business interruptions due to environmental damage and
    contamination; and 
--  The ability to enter into or continue leases. 

The foregoing list of risks is not exhaustive. Additional information concerning these and other factors which could impact Paramount and Cavalier are included in Paramount's most recent Annual Information Form. Although Paramount believes that the expectations reflected in such forward looking statements are reasonable, undue reliance should not be placed on them as Paramount cannot give any assurance that such expectations will prove to be correct. The forward-looking statements in this news release are made as of the date hereof and, except as required by applicable securities law, Paramount undertakes no obligation to update publicly or revise such statements, whether as a result of new information, future events or otherwise.

Contacts:
Paramount Resources Ltd.
J.H.T. (Jim) Riddell
President and Chief Operating Officer
403.290.3600

Paramount Resources Ltd.
B.K. (Bernie) Lee
Chief Financial Officer
403.290.3600
www.paramountres.com

Contacts:
Cavalier Energy Inc.
William Roach
President & Chief Executive Officer
403.268.3940
www.cavalierenergy.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Cloud Expo Breaking News
After a couple of false starts, cloud-based desktop solutions are picking up steam, driven by trends such as BYOD and pervasive high-speed connectivity. In his session at 15th Cloud Expo, Seth Bostock, CEO of IndependenceIT, cuts through the hype and the acronyms, and discusses the emergence of full-featured cloud workspaces that do for the desktop what cloud infrastructure did for the server. He’ll discuss VDI vs DaaS, implementation strategies and evaluation criteria.
Cloud computing started a technology revolution; now DevOps is driving that revolution forward. By enabling new approaches to service delivery, cloud and DevOps together are delivering even greater speed, agility, and efficiency. No wonder leading innovators are adopting DevOps and cloud together! In his session at DevOps Summit, Andi Mann, Vice President of Strategic Solutions at CA Technologies, will explore the synergies in these two approaches, with practical tips, techniques, research data, war stories, case studies, and recommendations.
Cloud Computing is evolving into a Big Three of Amazon Web Services, Google Cloud, and Microsoft Azure. Cloud 360: Multi-Cloud Bootcamp, being held Nov 4–5, 2014, in conjunction with 15th Cloud Expo in Santa Clara, CA, delivers a real-world demonstration of how to deploy and configure a scalable and available web application on all three platforms. The Cloud 360 Bootcamp, led by Janakiram MSV, an analyst with Gigaom Research, is the first bootcamp that introduces the core concepts of Infrastructure as a Service (IaaS) based on the workings of the Big Three platforms – Amazon EC2, Google Compute Engine, and Azure VMs. Bootcamp attendees will get to see the big picture and also receive the knowledge needed to make the best cloud decisions for their business applications and entire enterprise IT organization.
Scott Jenson leads a project called The Physical Web within the Chrome team at Google. Project members are working to take the scalability and openness of the web and use it to talk to the exponentially exploding range of smart devices. Nearly every company today working on the IoT comes up with the same basic solution: use my server and you'll be fine. But if we really believe there will be trillions of these devices, that just can't scale. We need a system that is open a scalable and by using the URL as a basic building block, we open this up and get the same resilience that the web enjoys.
The Internet of Things is a natural complement to the cloud and related technologies such as Big Data, analytics, and mobility. In his session at Internet of @ThingsExpo, Joe Weinman will lay out four generic strategies – digital disciplines – to exploit emerging digital technologies for strategic advantage. Joe Weinman has held executive leadership positions at Bell Labs, AT&T, Hewlett-Packard, and Telx, in areas such as corporate strategy, business development, product management, operations, and R&D.
SYS-CON Events announced today that DevOps.com has been named “Media Sponsor” of SYS-CON's “DevOps Summit at Cloud Expo,” which will take place on June 10–12, 2014, at the Javits Center in New York City, New York. DevOps.com is where the world meets DevOps. It is the largest collection of original content relating to DevOps on the web today Featuring up-to-the-minute news, feature stories, blogs, bylined articles and more, DevOps.com is where the thought leaders of the DevOps movement make their ideas known.
There are 182 billion emails sent every day, generating a lot of data about how recipients and ISPs respond. Many marketers take a more-is-better approach to stats, preferring to have the ability to slice and dice their email lists based numerous arbitrary stats. However, fundamentally what really matters is whether or not sending an email to a particular recipient will generate value. Data Scientists can design high-level insights such as engagement prediction models and content clusters that allow marketers to cut through the noise and design their campaigns around strong, predictive signals, rather than arbitrary statistics. SendGrid sends up to half a billion emails a day for customers such as Pinterest and GitHub. All this email adds up to more text than produced in the entire twitterverse. We track events like clicks, opens and deliveries to help improve deliverability for our customers – adding up to over 50 billion useful events every month. While SendGrid data covers only abo...
SYS-CON Events announced today that the Web Host Industry Review has been named “Media Sponsor” of SYS-CON's 15th International Cloud Expo®, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Since 2000, The Web Host Industry Review has made a name for itself as the foremost authority of the Web hosting industry providing reliable, insightful and comprehensive news, reviews and resources to the hosting community. TheWHIR Blogs provides a community of expert industry perspectives. The Web Host Industry Review Magazine also offers a business-minded, issue-driven perspective of interest to executives and decision-makers. WHIR TV offers on demand web hosting video interviews and web hosting video features of the key persons and events of the web hosting industry. WHIR Events brings together like-minded hosting industry professionals and decision-makers in local communities. TheWHIR is an iNET Interactive property.
SYS-CON Events announced today that O'Reilly Media has been named “Media Sponsor” of SYS-CON's 15th International Cloud Expo®, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. O'Reilly Media spreads the knowledge of innovators through its books, online services, magazines, and conferences. Since 1978, O'Reilly Media has been a chronicler and catalyst of cutting-edge development, homing in on the technology trends that really matter and spurring their adoption by amplifying "faint signals" from the alpha geeks who are creating the future. An active participant in the technology community, the company has a long history of advocacy, meme-making, and evangelism.
SYS-CON Events announced today that Verizon has been named “Gold Sponsor” of SYS-CON's 15th International Cloud Expo®, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Verizon Enterprise Solutions creates global connections that generate growth, drive business innovation and move society forward. With industry-specific solutions and a full range of global wholesale offerings provided over the company's secure mobility, cloud, strategic networking and advanced communications platforms, Verizon Enterprise Solutions helps open new opportunities around the world for innovation, investment and business transformation. Visit verizonenterprise.com to learn more.
SYS-CON Events announced today that TMCnet has been named “Media Sponsor” of SYS-CON's 15th International Cloud Expo®, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Technology Marketing Corporation (TMC) is the world's leading business to business and integrated marketing media company, servicing niche markets within the communications and technology industries.
"In my session I spoke about enterprise cloud analytics and how we can leverage analytics as a service," explained Ajay Budhraja, CTO at the Department of Justice, in this SYS-CON.tv interview at the 14th International Cloud Expo®, held June 10-12, 2014, at the Javits Center in New York City. Cloud Expo® 2014 Silicon Valley, November 4–6, at the Santa Clara Convention Center in Santa Clara, CA, will feature technical sessions from a rock star conference faculty and the leading Cloud industry players in the world.
“We are starting to see people move beyond the commodity cloud and enterprises need to start focusing on additional value added services in order to really drive their adoption," explained Jason Mondanaro, Director of Product Management at MetraTech, in this SYS-CON.tv interview at the 14th International Cloud Expo®, held June 10-12, 2014, at the Javits Center in New York City. Cloud Expo® 2014 Silicon Valley, November 4–6, at the Santa Clara Convention Center in Santa Clara, CA, will feature technical sessions from a rock star conference faculty and the leading Cloud industry players in the world.
"We are automated capacity control software, which basically looks at all the supply and demand and running a virtual cloud environment and does a deep analysis of that and says where should things go," explained Andrew Hillier, Co-founder & CTO of CiRBA, in this SYS-CON.tv interview at the 14th International Cloud Expo®, held June 10-12, 2014, at the Javits Center in New York City. Cloud Expo® 2014 Silicon Valley, November 4–6, at the Santa Clara Convention Center in Santa Clara, CA, will feature technical sessions from a rock star conference faculty and the leading Cloud industry players in the world.
Almost everyone sees the potential of Internet of Things but how can businesses truly unlock that potential. The key will be in the ability to discover business insight in the midst of an ocean of Big Data generated from billions of embedded devices via Systems of Discover. Businesses will also need to ensure that they can sustain that insight by leveraging the cloud for global reach, scale and elasticity. In his session at Internet of @ThingsExpo, Mac Devine, Distinguished Engineer at IBM, will discuss bringing these three elements together via Systems of Discover.