Click here to close now.

Welcome!

Big Data Journal Authors: Jon McNeill, Carmen Gonzalez, Elizabeth White, Pat Romanski, Martin Etmajer

News Feed Item

Alderon Announces Feasibility Study Results Demonstrating $3.244 Billion NPV and 29.3% IRR for the Kami Project

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 01/09/13 -- Alderon Iron Ore Corp. (TSX:ADV)(NYSE MKT:AXX) ("Alderon") is pleased to announce that it has received the results of the Feasibility Study ("FS") on the Rose Deposit of the Kamistiatusset ("Kami") Iron Ore Property in western Labrador. The FS was completed by BBA Inc. ("BBA") located in Montreal, Quebec, Stantec Consulting Ltd. ("Stantec") located in St. John's, Newfoundland & Labrador and Watts, Griffis and McOuat Limited ("WGM") located in Toronto, Ontario, and is effective as of December 17, 2012. The National Instrument (NI) 43-101 compliant Report (the "Report") summarizing the results of the FS will be filed on SEDAR and Alderon's website within 45 days of this news release. Results of the FS disclosed in this press release are in USD and pre-tax (except where otherwise indicated).

Highlights of the FS include:


----------------------------------------------------------------------------
NPV at 8% discount rate                                        $     3,244 M
----------------------------------------------------------------------------
IRR                                                                    29.3%
----------------------------------------------------------------------------
Total Estimated Capital Cost (excluding sustaining capital)    $   1,272.9 M
----------------------------------------------------------------------------
Average Estimated Operating Costs (loaded in ship Port of Sept-             
 Iles)                                                         $       42.17
----------------------------------------------------------------------------
FOB Concentrate Sales Price Forecast - based on long term CFR               
 benchmark price of $110/T @ 62% iron adjusted for Kami Fe                  
 grade and Hebei agreement terms                                            
 Year 1-5 (2016-2020)                                          $         107
 Year 6 onward                                                 $         102
----------------------------------------------------------------------------
Estimated Mine Life                                                 30 years
----------------------------------------------------------------------------
Final Product Iron Grade (%Fe)                                         65.2%
----------------------------------------------------------------------------
Measured and Indicated Resource of the Rose Deposit (COG=15%,               
 29.6% Total Iron)                                                 1093.2 Mt
----------------------------------------------------------------------------
Proven and Probable Reserves of the Rose Deposit (COG=15%,                  
 29.5% Total Iron)                                                  668.5 Mt
----------------------------------------------------------------------------
Annual Production Rate (average life of mine, post ramp-up                  
 year)                                                              8.0 Mtpa
----------------------------------------------------------------------------
Projected Plant Start-up and Commissioning                          Q4, 2015
----------------------------------------------------------------------------
Projected Commencement of Revenue Generation                        Q1, 2016
----------------------------------------------------------------------------
Projected Years to Payback at 8% discount rate                           3.8
----------------------------------------------------------------------------

"The completion of the Feasibility Study is a major milestone in Alderon's development and we are very pleased with the results. The completion of the Feasibility Study is another significant de-risking event that can be added to Alderon's confirmation of port access, Nalcor Stage III transmission line engineering and assessment agreement and strategic partnership with Hebei Iron and Steel ("Hebei")," says Tayfun Eldem, President and CEO of Alderon. "The study demonstrates robust economics on the Kami Property and the results meet all of the threshold criteria under our agreements with Hebei. Our schedule anticipates receipt of permits toward the end of 2013 and construction to follow immediately, with initial production in Q4 2015."

The FS demonstrates very attractive project economics. Based on a production rate of 8 million tonnes per year of iron ore concentrate at a grade of 65.2% iron, the FS shows a Net Present Value ("NPV") of $3.244 billion at a cash flow discount rate of 8%. The internal rate of return ("IRR") for the project is 29.3%. The level of accuracy of the FS is considered to be +/-15% and a foreign exchange rate of $1.00US = $1.00CDN was used.

On an after-tax basis, the FS shows a NPV of $1.858 billion and payback period of 4.5 years at a cash flow discount rate of 8%. The after-tax IRR for the project is 23.1%. The after-tax analysis is based on a number of assumptions which will be fully set out in the Report.

Financial Analysis

Based on the assumption that commercial production would begin in Q4 2015 and would continue for 30 years, the following results were obtained (pre-tax):


----------------------------------------------------------
IRR                         29.3%                         
----------------------------------------------------------
                                        NPV        Payback
                                (Billion $)        (years)
Discount Rate 0%           $         11.545            3.1
----------------------------------------------------------
5%                         $          5.030            3.5
----------------------------------------------------------
8%                         $          3.244            3.8
----------------------------------------------------------
10%                        $          2.461            4.0
----------------------------------------------------------

Total capital expenditures (including contingency) are estimated at $1.27 billion. The capital cost estimate excludes closure costs and sustaining capital, which are expected to be in the order of $48.1 million and $642.4 million respectively for the life of the project. These costs are included in the financial analysis for the project.


-----------------------------------------------------------------------
Summary of Estimated Initial Capital Costs (Million $)                 
-----------------------------------------------------------------------
Mining Capitalized Pre-Stripping Costs                      $      52.7
-----------------------------------------------------------------------
Concentrator and Site Infrastructure                        $     585.1
-----------------------------------------------------------------------
Environmental & Tailings Management                         $      47.4
-----------------------------------------------------------------------
Rail Line (Kami Site)                                       $      57.7
-----------------------------------------------------------------------
Port Facilities                                             $     152.2
-----------------------------------------------------------------------
Indirect Costs (Including Owner's Costs)                    $     258.8
-----------------------------------------------------------------------
Contingency                                                 $     119.0
-----------------------------------------------------------------------
TOTAL                                                       $   1,272.9
-----------------------------------------------------------------------

The FS assumes a Concentrate FOB selling price of $107/tonne for year 1-5 (2016-2020) and $102/tonne from year 6 onwards. The selling price is loaded in ship at Port of Sept-Iles with Fe premiums and Hebei discount applied. Average life-of-mine ("LOM") operating costs, including annual costs for leasing of equipment (purchase value of $176.9 million), are estimated at $42.17/tonne of concentrate. During the life of the project, leased equipment are replaced as they reach the end of their service life and these replacement costs are capitalized and reflected as part of the sustaining capital expenditures. Average LOM operating costs are based on the following:


---------------------------------------------------------------
Summary of Estimated Operating Costs ($/t of concentrate)      
---------------------------------------------------------------
Mining                                                   $17.11
---------------------------------------------------------------
Processing                                               $ 6.51
---------------------------------------------------------------
Site General                                             $ 0.34
---------------------------------------------------------------
General & Administrative                                 $ 1.50
---------------------------------------------------------------
Environmental & Tailings Management                      $ 0.52
---------------------------------------------------------------
Rail Transportation                                      $13.33
---------------------------------------------------------------
Port & Shiploading                                       $ 2.86
---------------------------------------------------------------
TOTAL                                                    $42.17
---------------------------------------------------------------

Mineral Resources and Mineral Reserves

The mineral resources and mineral reserves are reported in accordance with Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources Mineral Reserves and their Guidelines, and are compliant with NI 43-101.

The mineral resource estimate for the Kami Property is set out below. WGM was retained to audit an in-house estimate completed by Alderon. Mr. Michael Kociumbas, P.Geo. and Mr. Richard Risto, P.Geo. with independent firm, WGM, are Qualified Persons as defined by NI 43-101 and are responsible for reviewing and approving this mineral resource estimate and the QA/QC associated with the estimate. They have verified, reviewed and approved the technical data contained in this news release and underlying sampling, analytical and test data. The mineral resource estimate has been prepared using a 15% Total Fe cut-off grade, is effective December 17, 2012 and inclusive of mineral reserves.


---------------------------------------------------------------------------
                                 Tonnes                                    
Zone               Category   (Million)        TFe%      magFe%       hmFe%
---------------------------------------------------------------------------
Rose Central       Measured       249.9        29.4        17.6         8.1
---------------------------------------------------------------------------
                  Indicated       294.5        28.5        17.7         5.9
---------------------------------------------------------------------------
                  Total M&I       544.4        28.9        17.7         6.9
---------------------------------------------------------------------------
                                                                           
---------------------------------------------------------------------------
                   Inferred       160.7        28.9        16.9         7.1
---------------------------------------------------------------------------
                                                                           
---------------------------------------------------------------------------
Rose North         Measured       236.3        30.3        13.0        14.7
---------------------------------------------------------------------------
                  Indicated       312.5        30.5        11.8        17.1
---------------------------------------------------------------------------
                  Total M&I       548.8        30.4        12.3        16.1
---------------------------------------------------------------------------
                                                                           
---------------------------------------------------------------------------
                   Inferred       287.1        29.8        12.5        15.5
---------------------------------------------------------------------------
                                                                           
---------------------------------------------------------------------------
Mills Lake         Measured        50.7        30.5        21.5         7.0
---------------------------------------------------------------------------
                  Indicated       130.6        29.5        20.9         3.9
---------------------------------------------------------------------------
                  Total M&I       181.3        29.8        21.1         4.8
---------------------------------------------------------------------------
                                                                           
---------------------------------------------------------------------------
                   Inferred        74.8        29.3        20.3         2.7
---------------------------------------------------------------------------

The mining engineering work performed for this FS was based on the 3-D block model provided by Alderon and audited by WGM. Pit optimizations were performed on Measured and Indicated Resources and the pit shell having the optimal discounted NPV and strip ratio at a cut-off grade of 15% Total Fe was selected for the mineral reserve estimate. The final mineral reserve was estimated after applying engineering and operational design parameters. BBA is of the opinion that the mineral reserve estimate derived in this FS reasonably quantifies the economical ore mineralization of the Rose Deposit. The reserve estimate is as of December 17, 2012 and the mineral reserves presented in the table below are included in the mineral resource estimate set out above. Only the Measured and Indicated Resources within the Rose Central and the Rose North Deposits have been considered in the FS and have been used for the estimation of mineral reserves. The mineral resources within the Mills Lake Deposit have not been considered in the FS.


---------------------------------------------------------------------------
Category                 Mt        TFe%       WREC%      magFe%        MAG%
---------------------------------------------------------------------------
Proven                431.7        29.7        35.5        15.5        21.4
---------------------------------------------------------------------------
Probable              236.8        29.2        34.1        14.9        20.5
---------------------------------------------------------------------------
Total                 668.5        29.5        35.0        15.3        21.1
---------------------------------------------------------------------------

Project Summary

The Kami Property is located approximately 10 km from the town of Wabush in Western Labrador and approximately 6 km south from the Wabush Mines mining lease owned by Cliffs Natural Resources Inc. The proposed project at the Kami site, as stated in the FS, includes the following components:


--  The Rose ore deposit and waste rock disposal areas. 
--  Processing infrastructure including a crushing and grinding circuit,
    spiral plant, magnetite plant, and fine tailings thickener. 
--  Tailings Management Facility. 
--  Ancillary infrastructure to support the mine and process plant (gate and
    guardhouse, reclaim water pumphouse, truck wash bay and repair shop,
    electrical substation, administration/office buildings, maintenance
    offices, warehouse area and employee facilities, conveyors, loadout
    silo, stockpiles, sewage and effluent water treatment systems, mobile
    equipment and transmission lines). 
--  A temporary construction camp is located off-site. 
--  The rail infrastructure, including the rail line connecting to Quebec
    North Shore & Labrador (QNSL) Railway, the rail loop and the service
    tracks consist of a total of 25 km of new track passing to the south and
    east of the Town of Wabush. 
--  Nalcor will provide power directly to the Kami site main substation by
    means of a 315 kV transmission line.

Facilities at the Port will include:


--  A rail transportation component consisting of a Sept-Iles Junction
    interchange, railway line and staging tracks. 
--  A car dumper. 
--  A stacker/reclaimer system. 
--  A concentrate storage area with a capacity of 550,000 tonnes. 
--  A conveyor system feeding the future common deep water shiploading
    facility, capable of loading high capacity vessels destined for Asia,
    operated by the Port of Sept-Iles.

The proposed project will produce eight million metric tonnes of iron ore concentrate per year and will ship concentrate to market via the Port of Sept-Iles facilities at Pointe Noire, Quebec. Ore processing will take place at the Kami site and will involve the following steps:


--  Ore will be mined from the open pit mine using conventional drill and
    blast techniques and transported via haul trucks; 
--  Ore will be hauled to the primary crusher in proximity of the pit and
    the crushed ore will be delivered to the stockpile and to the process
    plant via conveyor; 
--  The process plant will include grinding, screening, and gravity and
    magnetic concentration; 
--  Tailings (process waste) will be pumped to the tailings impoundment area
    south of the process plant; and 
--  Iron ore concentrate will be loaded onto gondola rail cars for
    transportation to the Port of Sept-Iles where it will be stockpiled and
    in turn transferred to ships for delivery to market.

Development Timetable

A construction schedule has been established that is contingent on the following milestones to be realized:


-------------------------------------------------------------
Major Milestones                                         Date
-------------------------------------------------------------
Interim Engineering & Planning Services Agreement    Aug-2012
-------------------------------------------------------------
Start Detailed Engineering                           Nov-2012
-------------------------------------------------------------
EA Release                                           Sep-2013
-------------------------------------------------------------
Permits and Start Construction                       Nov-2013
-------------------------------------------------------------
Construction Completed                               Aug-2015
-------------------------------------------------------------
Power Availability (NL)                              Sep-2015
-------------------------------------------------------------
Full Handover to Operations                          Nov-2015
-------------------------------------------------------------

The environmental permitting process began with project registration initiated with the submission of the project description in October 2011. An environmental impact statement was submitted in September 2012 and based on the expected duration of the various regulatory proceedings, it is expected that the permits, which will allow construction, will be issued in November 2013. No site work is anticipated prior to this date. Construction is set to start in November 2013 and is based on a construction schedule of 24 months including Pre-Operational Verifications and plant handover to operations.

The documents filed by Alderon in the Environmental Assessment process include provision to increase planned production to 16 million tonnes per year. However, the FS only contemplates an 8 million tonne per year production scenario. Alderon intends to proceed with the 8 million tonne per year production scenario outlined in the FS and it may evaluate the feasibility of a 16 million tonne per year production scenario after the commencement of commercial production at the Kami Property. Such evaluation will be based on several factors including market projections for iron ore supply and demand.

Analyst and Shareholder Conference Call

Alderon will host a conference call today at 8:00 a.m., EST (January 9, 2013) to discuss the FS results. To participate in the call please dial the following:


Toronto: 416-623-0333                                                       
Montreal: 514-687-4017                                                      
Vancouver: 604-681-8564                                                     
Calgary or International: 403-532-5601                                      
                                                                            
Toll Free North America: 1-855-353-9183                                     
                                                                            
Participant Pass Code: 43764#                                               

Technical Report and Qualified Person

A NI 43-101 Technical Report will be filed on SEDAR and on Alderon's website within 45 days of the date of this news release. The Report will consist of a summary of the Feasibility Study. The Report is being prepared under the supervision of Angelo Grandillo, P.Eng, of BBA, a Qualified Person as defined by NI 43-101, with contributions from Stantec and WGM. Mr. Grandillo is a Qualified Person as defined by NI 43-101 and Mr. Grandillo is independent of Alderon. Mr. Grandillo has reviewed and approved the technical information contained in this news release, with the exception of the mineral resource estimate which was reviewed and approved by WGM as noted above. Mr. Grandillo has verified all the data underlying the technical information disclosed in this news release.

About Alderon

Alderon is a leading iron ore development company in Canada with offices in Vancouver, Toronto, Montreal, Labrador City and St. John's. The 100% owned Kami Project is located within Canada's premier iron ore district and is surrounded by four producing iron ore mines. The Alderon team is comprised of skilled professionals with significant iron ore expertise to advance Kami towards production.

Prior to the release of the Report on the FS results, additional information about the Kami Project can be found in the technical report filed on SEDAR at www.sedar.com entitled: "Technical Report Preliminary Economic Assessment of the Rose Central Deposit and Resource Estimate for the Rose Central, Rose North and Mills Deposits of the Kamistiatusset (Kami) Iron Ore Property, Labrador for Alderon Iron Ore Corp." dated effective October 26, 2011.

For more information on Alderon, please visit our website at www.alderonironore.com.

ALDERON IRON ORE CORP.

On behalf of the Board

Mark J. Morabito, Executive Chairman

Cautionary Note Regarding Forward-Looking Information

This press release contains "forward-looking information" concerning anticipated developments and events that may occur in the future. Forward looking information contained in this press release include, but are not limited to, statements with respect to: (i) the estimation of mineral resources and mineral reserves; (ii) the market and future price of iron ore and related products; (iii) success of exploration activities; (iv) the completion and timing of the permitting and environmental assessment process; (v) the negotiation and conclusion of infrastructure contracts; (vi) expected infrastructure requirements; and (vii) the results of the FS including statements about future production, future operating and capital costs, the projected IRR, NPV, payback period, construction timelines and production timelines for the Kami Property.

In certain cases, forward-looking information can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions or statements about future events or performance. Forward-looking information contained in this press release is based on certain factors and assumptions regarding, among other things, the estimation of mineral reserves and resources, the realization of resource estimates, iron ore and other metal prices, the timing and amount of future exploration and development expenditures, the estimation of initial and sustaining capital requirements, the estimation of labour and operating costs, the availability of necessary financing and materials to continue to explore and develop the Kami Property (as defined herein) in the short and long-term, the progress of exploration and development activities, the receipt of necessary regulatory approvals, the completion of the environmental assessment process, the estimation of insurance coverage, and assumptions with respect to currency fluctuations, environmental risks, title disputes or claims, and other similar matters. While the Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include risks inherent in the exploration and development of mineral deposits, including risks relating to changes in project parameters as plans continue to be redefined including the possibility that mining operations may not commence at the Kami Property, risks relating to variations in mineral resources, grade or recovery rates resulting from current exploration and development activities, risks relating to the ability to access rail transportation, sources of power and port facilities, risks relating to changes in iron ore prices and the worldwide demand for and supply of iron ore and related products, risks related to increased competition in the market for iron ore and related products and in the mining industry generally, risks related to current global financial conditions, uncertainties inherent in the estimation of mineral resources, access and supply risks, reliance on key personnel, operational risks inherent in the conduct of mining activities, including the risk of accidents, labour disputes, increases in capital and operating costs and the risk of delays or increased costs that might be encountered during the development process, regulatory risks, including risks relating to the acquisition of the necessary licences and permits, financing, capitalization and liquidity risks, including the risk that the financing necessary to fund the exploration and development activities at the Kami Property may not be available on satisfactory terms, or at all, risks related to disputes concerning property titles and interest, environmental risks, and the additional risks identified in the "Risk Factors" section of the Company's Annual Information Form for the most recently completed financial year or other reports and filings applicable with Canadian securities regulators. Accordingly, readers should not place undue reliance on forward-looking information. The forward-looking information is made as of the date of this press release. Except as required by applicable securities laws, the Company does not undertake any obligation to publicly update or revise any forward-looking information.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@BigDataExpo Stories
We certainly live in interesting technological times. And no more interesting than the current competing IoT standards for connectivity. Various standards bodies, approaches, and ecosystems are vying for mindshare and positioning for a competitive edge. It is clear that when the dust settles, we will have new protocols, evolved protocols, that will change the way we interact with devices and infrastructure. We will also have evolved web protocols, like HTTP/2, that will be changing the very core...
Operational Hadoop and the Lambda Architecture for Streaming Data Apache Hadoop is emerging as a distributed platform for handling large and fast incoming streams of data. Predictive maintenance, supply chain optimization, and Internet-of-Things analysis are examples where Hadoop provides the scalable storage, processing, and analytics platform to gain meaningful insights from granular data that is typically only valuable from a large-scale, aggregate view. One architecture useful for capturing...
Docker is an excellent platform for organizations interested in running microservices. It offers portability and consistency between development and production environments, quick provisioning times, and a simple way to isolate services. In his session at DevOps Summit at 16th Cloud Expo, Shannon Williams, co-founder of Rancher Labs, will walk through these and other benefits of using Docker to run microservices, and provide an overview of RancherOS, a minimalist distribution of Linux designed...
SYS-CON Events announced today that Vitria Technology, Inc. will exhibit at SYS-CON’s @ThingsExpo, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Vitria will showcase the company’s new IoT Analytics Platform through live demonstrations at booth #330. Vitria’s IoT Analytics Platform, fully integrated and powered by an operational intelligence engine, enables customers to rapidly build and operationalize advanced analytics to deliver timely business outcomes ...
SYS-CON Events announced today that Dyn, the worldwide leader in Internet Performance, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Dyn is a cloud-based Internet Performance company. Dyn helps companies monitor, control, and optimize online infrastructure for an exceptional end-user experience. Through a world-class network and unrivaled, objective intelligence into Internet conditions, Dyn ensures...
Containers and microservices have become topics of intense interest throughout the cloud developer and enterprise IT communities. Accordingly, attendees at the upcoming 16th Cloud Expo at the Javits Center in New York June 9-11 will find fresh new content in a new track called PaaS | Containers & Microservices Containers are not being considered for the first time by the cloud community, but a current era of re-consideration has pushed them to the top of the cloud agenda. With the launch ...
CommVault has announced that top industry technology visionaries have joined its leadership team. The addition of leaders from companies such as Oracle, SAP, Microsoft, Cisco, PwC and EMC signals the continuation of CommVault Next, the company's business transformation for sales, go-to-market strategies, pricing and packaging and technology innovation. The company also announced that it had realigned its structure to create business units to more directly match how customers evaluate, deploy, op...
In their session at @ThingsExpo, Shyam Varan Nath, Principal Architect at GE, and Ibrahim Gokcen, who leads GE's advanced IoT analytics, focused on the Internet of Things / Industrial Internet and how to make it operational for business end-users. Learn about the challenges posed by machine and sensor data and how to marry it with enterprise data. They also discussed the tips and tricks to provide the Industrial Internet as an end-user consumable service using Big Data Analytics and Industrial C...
Thanks to Docker, it becomes very easy to leverage containers to build, ship, and run any Linux application on any kind of infrastructure. Docker is particularly helpful for microservice architectures because their successful implementation relies on a fast, efficient deployment mechanism – which is precisely one of the features of Docker. Microservice architectures are therefore becoming more popular, and are increasingly seen as an interesting option even for smaller projects, instead of bein...
Performance is the intersection of power, agility, control, and choice. If you value performance, and more specifically consistent performance, you need to look beyond simple virtualized compute. Many factors need to be considered to create a truly performant environment. In his General Session at 15th Cloud Expo, Harold Hannon, Sr. Software Architect at SoftLayer, discussed how to take advantage of a multitude of compute options and platform features to make cloud the cornerstone of your onlin...
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @Things...
Even as cloud and managed services grow increasingly central to business strategy and performance, challenges remain. The biggest sticking point for companies seeking to capitalize on the cloud is data security. Keeping data safe is an issue in any computing environment, and it has been a focus since the earliest days of the cloud revolution. Understandably so: a lot can go wrong when you allow valuable information to live outside the firewall. Recent revelations about government snooping, along...
SYS-CON Media announced that IBM, which offers the world’s deepest portfolio of technologies and expertise that are transforming the future of work, has launched ad campaigns on SYS-CON’s numerous online magazines such as Cloud Computing Journal, Virtualization Journal, SOA World Magazine, and IoT Journal. IBM’s campaigns focus on vendors in the technology marketplace, the future of testing, Big Data and analytics, and mobile platforms.
In his session at DevOps Summit, Tapabrata Pal, Director of Enterprise Architecture at Capital One, will tell a story about how Capital One has embraced Agile and DevOps Security practices across the Enterprise – driven by Enterprise Architecture; bringing in Development, Operations and Information Security organizations together. Capital Ones DevOpsSec practice is based upon three "pillars" – Shift-Left, Automate Everything, Dashboard Everything. Within about three years, from 100% waterfall, C...
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @Things...
The Internet of Things (IoT) is rapidly in the process of breaking from its heretofore relatively obscure enterprise applications (such as plant floor control and supply chain management) and going mainstream into the consumer space. More and more creative folks are interconnecting everyday products such as household items, mobile devices, appliances and cars, and unleashing new and imaginative scenarios. We are seeing a lot of excitement around applications in home automation, personal fitness,...
Data-intensive companies that strive to gain insights from data using Big Data analytics tools can gain tremendous competitive advantage by deploying data-centric storage. Organizations generate large volumes of data, the vast majority of which is unstructured. As the volume and velocity of this unstructured data increases, the costs, risks and usability challenges associated with managing the unstructured data (regardless of file type, size or device) increases simultaneously, including end-to-...
Every innovation or invention was originally a daydream. You like to imagine a “what-if” scenario. And with all the attention being paid to the so-called Internet of Things (IoT) you don’t have to stretch the imagination too much to see how this may impact commercial and homeowners insurance. We’re beyond the point of accepting this as a leap of faith. The groundwork is laid. Now it’s just a matter of time. We can thank the inventors of smart thermostats for developing a practical business a...
The excitement around the possibilities enabled by Big Data is being tempered by the daunting task of feeding the analytics engines with high quality data on a continuous basis. As the once distinct fields of data integration and data management increasingly converge, cloud-based data solutions providers have emerged that can buffer your organization from the complexities of this continuous data cleansing and management so that you’re free to focus on the end goal: actionable insight.
When it comes to the Internet of Things, hooking up will get you only so far. If you want customers to commit, you need to go beyond simply connecting products. You need to use the devices themselves to transform how you engage with every customer and how you manage the entire product lifecycle. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, will show how “product relationship management” can help you leverage your connected devices and the data th...